United States › Grid › Interconnection queues › Massachusetts

SOLAR + STORAGE · ISO-NE

Solar plus Battery

Solar plus Battery is a 2.8 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2022 (completed)
  2. Withdrawn / abandonedAug 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1260
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 13.8 kV Line 19S1
Location
Hampden County, Massachusetts
Technology
Solar: 2.8 MW · Battery
Total requested
2.8 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
6 May 2022
Proposed online date
June 2023
Withdrawn
August 2022

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County