United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 168

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 168 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
ELP Clay Storage
Battery storage · ELP Clay Storage LLC
165 MWWithdrawn / abandoned Onondaga, NYNYISO Feb 2023
Pampa Energy Center
Coal · Pampa Energy Center, LLC
165 MWWithdrawn / abandoned ERCOT May 2005target 2050
Brunswick Energy Storage
Battery storage · East Coast Power LLC
165 MWWithdrawn / abandoned Union, NJNYISO Sep 2021
Solar project 584, Fayette County
Solar
165 MWWithdrawn / abandoned Fayette, TNSoutheast Sep 2023target 2009
Alder Creek Solar
Solar · Alder Creek Solar, LLC
165 MWWithdrawn / abandoned Oneida, NYNYISO May 2018
Gas project Q8, Coconino County
Gas
165 MWWithdrawn / abandoned Coconino, AZWest Jul 2005target 2008
Battery storage project GEN-2023-036, Jackson County
Battery storage
165 MWWithdrawn / abandoned Jackson, MOSPP Oct 2023target 2026
Onshore wind project J3020, Lyon County
Onshore wind
165 MWWithdrawn / abandoned Lyon, MNMISO Sep 2022target 2027
Bowhead Solar
Solar · Baffin Bay Solar, LLC
165 MWWithdrawn / abandoned Kleberg, TXERCOT Nov 2021target 2026
Other project G098, Butler County
Other
165 MWWithdrawn / abandoned Butler, OHMISO Jun 2001target 2002
Solar + storage project GEN-2021-086, Howard County
Solar + storage
165 MWWithdrawn / abandoned Howard, ARSPP Apr 2021target 2027
Surplus; J1669
Other
165 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Apr 2024target 2026
Other project G061, Jackson County
Other
165 MWWithdrawn / abandoned Jackson, ILMISO Sep 2000target 2003
Solar project IC-946, Macon County
Solar
165 MWWithdrawn / abandoned Macon, GASoutheast Apr 2021
Lynchpin Solar
Solar + storage
165 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Zenith BESS
Battery storage · Zenith Power LLC
165 MWWithdrawn / abandoned Onondaga, NYNYISO Sep 2024
Onshore wind project 112-A, Benton County
Onshore wind · Northwest Wind Partners
165 MWWithdrawn / abandoned Benton, WAWest Dec 2006target 2008
Solar project 187960, Darlington County
Solar · Duke Energy Progress, LLC
165 MWWithdrawn / abandoned Darlington, SCSoutheast Jul 2021
Solar project J2968, Jefferson Davis Parish County
Solar
165 MWWithdrawn / abandoned Jefferson Davis Parish, LAMISO Sep 2022target 2023
Geothermal project 258, Beaver County
Geothermal
165 MWWithdrawn / abandoned Beaver, UTWest Feb 2009target 2011
Onshore wind project J108, Ford County
Onshore wind
165 MWWithdrawn / abandoned Ford, ILMISO Dec 2009target 2010
Buffalo Rd. Wind Farm
Onshore wind · Invenergy Wind, LLC
165 MWWithdrawn / abandoned Wyoming, NYNYISO Feb 2005
Dusky Solar
Solar · Cypress Creek Renewables
165 MWWithdrawn / abandoned Hill, TXERCOT Jun 2018target 2020
Solar
Solar
165 MWWithdrawn / abandoned Somerset, MEISO-NE Jun 2024target 2028
Solar project AF2-079, Darke County
Solar
165 MWWithdrawn / abandoned Darke, OHPJM Jan 2020target 2023
Gas project Q9, Maricopa County
Gas
165 MWWithdrawn / abandoned Maricopa, AZWest Jul 2005target 2008
Other project L01_AEP137, Lawrence County
Other
165 MWWithdrawn / abandoned Lawrence, OHPJM Aug 2003target 2012
Coal project G567, Delta County
Coal
165 MWWithdrawn / abandoned Delta, MIMISO Nov 2005target 2007
Carta Valley Wind
Onshore wind · GE Energy
165 MWWithdrawn / abandoned ERCOT Nov 2008target 2050
Solar + storage project AH1-540, Ogle County
Solar + storage · Golden Harvest Energy, LLC
165 MWWithdrawn / abandoned Ogle, ILPJM Sep 2021target 2025
Solar project J2707, Assumption Parish County
Solar
165 MWWithdrawn / abandoned Assumption Parish, LAMISO Sep 2022target 2027
Solar project AE2-177, Elk County
Solar
165 MWWithdrawn / abandoned Elk, PAPJM Mar 2019target 2021
Harmony Storage 1
Battery storage
165 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2025
Other project GEN-2023-SR14, Ellis County
Other
165 MWWithdrawn / abandoned Ellis, KSSPP Feb 20232025
Gas project Q13, Yuma County
Gas
165 MWWithdrawn / abandoned Yuma, AZWest Aug 2005target 2008
Nuclear project GEN-2008-124N
Nuclear
165 MWWithdrawn / abandoned NESPP Nov 2008
Slate Mountain Solar
Solar + storage
165 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2027
Lago Domingo Solar
Solar + storage
165 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Solar project IC-457, Tift County
Solar
165 MWWithdrawn / abandoned Tift, GASoutheast May 2016
Solar project J2620, Ouachita County
Solar
164 MWWithdrawn / abandoned Ouachita, ARMISO Sep 2022target 2027
Solar project J2393, Coles County
Solar
164 MWWithdrawn / abandoned Coles, ILMISO Aug 2023target 2027
Solar project 375, Obion County
Solar
164 MWWithdrawn / abandoned Obion, TNSoutheast Jun 2019
Onshore wind project V2-026, Barbour County
Onshore wind
164 MWWithdrawn / abandoned Barbour, WVPJM Jun 2009target 2012
Solar project J1260, Desha County
Solar
164 MWWithdrawn / abandoned Desha, ARMISO Apr 2019target 2021
BRP Kotys BESS
Battery storage · BRP Kotys BESS LLC
163 MWWithdrawn / abandoned ERCOT Feb 2022target 2027
Solar project AG2-444, Pickaway County
Solar · Brook Trout Solar, LLC
163 MWWithdrawn / abandoned Pickaway, OHPJM Feb 2025target 2024
Gateway Bradford Plant
Gas
163 MWWithdrawn / abandoned Bradford, PAPJM Oct 2014target 2021
Solar + storage project IC-843, Ware County
Solar + storage
163 MWWithdrawn / abandoned Ware, GASoutheast Dec 2019target 2022
NY Mahopac 45 Margaret Rd Storage
Battery storage · Bluewave Storage Origination LLC
163 MWWithdrawn / abandoned Putnam, NYNYISO Aug 2022
Converts QP 164 to combined cycle facility and inc
Gas
162 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2007target 2014
Page 168 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)