COAL Β· ERCOT

Pampa Energy Center

Pampa Energy Center is a 165 MW coal request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2005 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
07INR0004
Grid region
ERCOT (Texas)
Developer
Pampa Energy Center, LLC
Technology
Coal: 165 MW
Total requested
165 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
17 May 2005
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem