United States › Grid › Interconnection queues › New Jersey
BATTERY STORAGE · NYISOBrunswick Energy Storage
Brunswick Energy Storage is a 165 MW battery storage request withdrawn in the NYISO interconnection queue, in Union County, New Jersey, connecting to ConEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedJan 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1262
- Grid region
- NYISO (New York)
- Utility / transmission owner
- ConEd
- Developer
- East Coast Power LLC
- Connection point (POI)
- Goethals 345kV
- Location
- Union County, New Jersey
- Technology
- Battery: 165 MW
- Total requested
- 165 MW
- Queue status
- Withdrawn
- Entered queue
- 24 September 2021
- Withdrawn
- January 2022
Location
Marker shows the centre of Union County; the queue data does not give exact sites.
Power plants in New Jersey · Transmission lines in New Jersey
Other requests in Union County
- Gas project AH1-722, Union CountyGas · 158 MW · in study
- Gas project AH1-715, Union CountyGas · 149 MW · in study
- Linden 1, 2 & 3Gas · 750 MW · built
- Linden 1, 2 & 3Gas · 436 MW · built
- Tosco #6Gas · 180 MW · built
- Linden 5 & 6Gas · 120 MW · built
- Linden Generating StationGas · 61.0 MW · built
- Linden Generating StationGas · 47.0 MW · built
- Linden 1 & 2Gas · 44.0 MW · built
- Linden Generating StationGas · 36.0 MW · built
- Linden Generating StationGas · 23.0 MW · built
- Tosco #6Gas · 20.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem