United States βΊ Grid βΊ Interconnection queues βΊ Washington
ONSHORE WIND Β· WESTOnshore wind project 112-A, Benton County
Onshore wind project 112-A, Benton County is a 165 MW onshore wind request withdrawn in the West interconnection queue, in Benton County, Washington, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2006 (completed)
- Withdrawn / abandonedFeb 2012 (project stopped here)
- ConsentedJun 2008 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 112-A
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- Northwest Wind Partners
- Connection point (POI)
- Union Gap - Midway
- Location
- Benton County, Washington
- Technology
- Wind: 165 MW
- Total requested
- 165 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA signed 6/11/08, Suspended 2/24/09, Terminated 2/25/12
- Queue status
- Withdrawn
- Entered queue
- 12 December 2006
- Agreement signed
- 11 June 2008
- Proposed online date
- September 2008
- Withdrawn
- February 2012
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Power plants in Washington Β· Transmission lines in Washington
Other requests in Benton County
- Solar + storage project G0822, Benton CountySolar + storage Β· 4,000 MW Β· in study
- Nuclear project G0998, Benton CountyNuclear Β· 1,120 MW Β· in study
- Solar + storage project G0670, Benton CountySolar + storage Β· 1,000 MW Β· in study
- Solar + storage project G0688, Benton CountySolar + storage Β· 1,000 MW Β· in study
- Solar + storage project G1040, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G0932, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G1037, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G1039, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G0920, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G0933, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G1038, Benton CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project G0684, Benton CountySolar + storage Β· 705 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem