United States βΊ Grid βΊ Interconnection queues βΊ Missouri
BATTERY STORAGE Β· SPPBattery storage project GEN-2023-036, Jackson County
Battery storage project GEN-2023-036, Jackson County is a 165 MW battery storage request withdrawn in the SPP interconnection queue, in Jackson County, Missouri, connecting to INDN.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedAug 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2023-036
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- INDN
- Connection point (POI)
- Eckles Road 161 kV Substation
- Location
- Jackson County, Missouri
- Technology
- Battery: 165 MW
- Total requested
- 165 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2026
- Withdrawn
- August 2025
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Battery storage project GEN-2018-031, Jackson CountyBattery storage Β· 50.0 MW Β· agreement signed
- Battery storage project GEN-2021-042, Jackson CountyBattery storage Β· 50.0 MW Β· agreement signed
- Gas project GEN-2024-207, Jackson CountyGas Β· 779 MW Β· in study
- Battery storage project GEN-2024-217, Jackson CountyBattery storage Β· 250 MW Β· in study
- Gas project GEN-2024-206, Jackson CountyGas Β· 226 MW Β· in study
- Battery storage project GEN-2022-144, Jackson CountyBattery storage Β· 200 MW Β· in study
- Battery storage project GEN-2024-074, Jackson CountyBattery storage Β· 200 MW Β· in study
- Battery storage project GEN-2024-352, Jackson CountyBattery storage Β· 199 MW Β· in study
- Battery storage project GEN-2023-171, Jackson CountyBattery storage Β· 150 MW Β· in study
- Other project GEN-2025-SR18, Jackson CountyOther Β· 50.0 MW Β· in study
- Solar project GEN-2021-SR9, Jackson CountySolar Β· 10.0 MW Β· built
- Gas project GEN-2000-008, Jackson CountyGas Β· 560 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem