Surplus; J1669

Surplus; J1669 is a 165 MW other request withdrawn in the MISO interconnection queue, in Jefferson Davis Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedJul 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
S1050
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
Lake Charles Bulk 38kV Tap
Location
Jefferson Davis Parish County, Louisiana
Technology
Other: 165 MW · Battery
Total requested
165 MW
Queue status
Withdrawn
Entered queue
4 April 2024
Proposed online date
May 2026
Withdrawn
July 2024

Location

Marker shows the centre of Jefferson Davis Parish County; the queue data does not give exact sites.