United States › Grid › Interconnection queues › Louisiana
OTHER · MISOSurplus; J1669
Surplus; J1669 is a 165 MW other request withdrawn in the MISO interconnection queue, in Jefferson Davis Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2024 (completed)
- Withdrawn / abandonedJul 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- S1050
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Lake Charles Bulk 38kV Tap
- Location
- Jefferson Davis Parish County, Louisiana
- Technology
- Other: 165 MW · Battery
- Total requested
- 165 MW
- Queue status
- Withdrawn
- Entered queue
- 4 April 2024
- Proposed online date
- May 2026
- Withdrawn
- July 2024
Location
Marker shows the centre of Jefferson Davis Parish County; the queue data does not give exact sites.
Other requests in Jefferson Davis Parish County
- Battery storage project J4076, Jefferson Davis Parish CountyBattery storage · 400 MW · in study
- Solar project J4051, Jefferson Davis Parish CountySolar · 220 MW · in study
- Solar project J4050, Jefferson Davis Parish CountySolar · 220 MW · in study
- Solar project J2967, Jefferson Davis Parish CountySolar · 200 MW · in study
- Solar project J1669, Jefferson Davis Parish CountySolar · 165 MW · in study
- Solar project J3781, Jefferson Davis Parish CountySolar · 150 MW · in study
- Battery storage project J4052, Jefferson Davis Parish CountyBattery storage · 100 MW · in study
- Solar project J2701, Jefferson Davis Parish CountySolar · 100 MW · in study
- Solar project J3914, Jefferson Davis Parish CountySolar · 85.0 MW · in study
- Solar project J3322, Jefferson Davis Parish CountySolar · 325 MW · withdrawn
- Onshore wind project J860, Jefferson Davis Parish CountyOnshore wind · 200 MW · withdrawn
- Solar project J2968, Jefferson Davis Parish CountySolar · 165 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem