SOLAR Β· MISO

Solar project J2968, Jefferson Davis Parish County

Solar project J2968, Jefferson Davis Parish County is a 165 MW solar request withdrawn in the MISO interconnection queue, in Jefferson Davis Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2968
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
LC Bulk to Henning 138kV Line (Circuit 28)
Location
Jefferson Davis Parish County, Louisiana
Technology
Solar: 165 MW
Total requested
165 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
12 September 2022
Proposed online date
September 2023
Withdrawn
July 2025

Location

Marker shows the centre of Jefferson Davis Parish County; the queue data does not give exact sites.