United States β€Ί Grid β€Ί Interconnection queues β€Ί Pennsylvania

SOLAR Β· PJM

Solar project AE2-177, Elk County

Solar project AE2-177, Elk County is a 165 MW solar request withdrawn in the PJM interconnection queue, in Elk County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2019 (completed)
  2. Withdrawn / abandonedApr 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AE2-177
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Squabb SVC 230 kV
Location
Elk County, Pennsylvania
Technology
Solar: 165 MW
Total requested
165 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
18 March 2019
Proposed online date
October 2021
Withdrawn
April 2019

Location

Marker shows the centre of Elk County; the queue data does not give exact sites.

Power plants in Pennsylvania Β· Transmission lines in Pennsylvania

Other requests in Elk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem