United States › Grid › Interconnection queues › Pennsylvania
BATTERY STORAGE · NYISOSeven Creek Energy - Squab Hollow
Seven Creek Energy - Squab Hollow is a 290 MW battery storage request withdrawn in the NYISO interconnection queue, in Elk County, Pennsylvania, connecting to NYSEG.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2019 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 933
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NYSEG
- Developer
- Seven Creek Energy, LLC
- Connection point (POI)
- Homer City - Pierce Brook 345kV
- Location
- Elk County, Pennsylvania
- Technology
- Battery: 290 MW
- Total requested
- 290 MW
- Queue status
- Withdrawn
- Entered queue
- 31 October 2019
- Withdrawn
- April 2021
Location
Marker shows the centre of Elk County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Elk County
- Solar project AI1-040, Elk CountySolar · 250 MW · in study
- Solar + storage project AI1-213, Elk CountySolar + storage · 174 MW · in study
- Jakes Hollow SolarSolar · 20.0 MW · suspended
- Gas project H24, Elk CountyGas · 575 MW · withdrawn
- PA-Fritz Kiln LLCSolar · 300 MW · withdrawn
- Gas project B44, Elk CountyGas · 240 MW · withdrawn
- Battery storage project AF1-306, Elk CountyBattery storage · 197 MW · withdrawn
- Solar project AE2-177, Elk CountySolar · 165 MW · withdrawn
- Solar project AF1-220, Elk CountySolar · 152 MW · withdrawn
- Onshore wind project W4-012, Elk CountyOnshore wind · 120 MW · withdrawn
- EL-Mefferts RunSolar · 20.0 MW · withdrawn
- Evergreen SolarSolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem