United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
NUCLEAR Β· SPPNuclear project GEN-2008-124N
Nuclear project GEN-2008-124N is a 165 MW nuclear request withdrawn in the SPP interconnection queue, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Nov 2008 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2008-124N
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Location
- Nebraska
- Technology
- Nuclear: 165 MW
- Total requested
- 165 MW
- Service type
- Energy only (ERIS)
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 20 November 2008
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem