United States β€Ί Grid β€Ί Interconnection queues

ONSHORE WIND Β· ERCOT

Carta Valley Wind

Carta Valley Wind is a 165 MW onshore wind request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2008 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
12INR0021
Grid region
ERCOT (Texas)
Developer
GE Energy
Technology
Wind: 165 MW
Total requested
165 MW
Study phase
FIS Complete
Queue status
Withdrawn
Entered queue
14 November 2008
Proposed online date
December 2050

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem