United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Solar interconnection queue in the USA — page 15

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 15 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1576, Washington Parish County
Solar
200 MWAgreement signed Washington Parish, LAMISO Mar 2022target 2026
Desert Rose Solar
Solar
200 MWPaused / redesign Andrews, TXERCOT Jun 2018
Solar project J1629, Columbia County
Solar
200 MWAgreement signed Columbia, WIMISO Jun 2020target 2027
Solar project IC-1195, Warren County
Solar
200 MWAgreement signed Warren, GASoutheast Oct 2023target 2028
Solar project J3719, Miami County
Solar
200 MWIn study Miami, INMISO Mar 2024target 2028
Solar project J1481, Howard County
Solar
200 MWAgreement signed Howard, INMISO Apr 2019target 2025
Solar project IC-1204, Jefferson County
Solar
200 MWAgreement signed Jefferson, GASoutheast Nov 2023target 2028
Solar project J1196, Sanilac County
Solar
200 MWAgreement signed Sanilac, MIMISO Apr 2019target 2025
Solar project J2526, Red River Parish County
Solar
200 MWIn study Red River Parish, LAMISO Sep 2022target 2026
Solar project 3RSC-2023-01, Pueblo County
Solar
200 MWIn study Pueblo, COWest May 2023target 2025
Solar project J1107, Cape Girardeau County
Solar
200 MWUnder construction Cape Girardeau, MOMISO Mar 2018target 2023
Solar project AH1-151, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Solar project 5RSC-2024-23, Pueblo County
Solar
200 MWIn study Pueblo, COWest Jan 2024target 2028
Solar project Q230, Navajo County
Solar
200 MWUnder construction Navajo, AZWest Sep 2015target 2021
Solar project IC-1180, Jones County
Solar
200 MWPaused / redesign Jones, MSSoutheast Oct 2023target 2028
Solar project J993, Boone County
Solar
200 MWUnder construction Boone, INMISO Mar 2018target 2023
Pleasant Prairie Solar Energy Center
Solar
200 MWAgreement signed Franklin, OHPJM Mar 2019target 2027
Solar project J1218, Muscatine County
Solar
200 MWAgreement signed Muscatine, IAMISO Apr 2019target 2026
Solar project GEN-2023-035, Grady County
Solar
200 MWIn study Grady, OKSPP Oct 2023target 2026
Solar project GEN-2022-055, Grady County
Solar
200 MWIn study Grady, OKSPP Jun 2022target 2029
Solar project J3919, Lincoln County
Solar
200 MWIn study Lincoln, MOMISO Mar 2025target 2030
Solar project J3286, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Apr 2024target 2028
Solar project J1007, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Mar 20182023
Solar project J2224, Iberville Parish County
Solar
200 MWIn study Iberville Parish, LAMISO Aug 2021target 2025
Solar project J1780, Montgomery County
Solar
200 MWIn study Montgomery, INMISO Jun 2020target 2026
Solar project J2485, Livingston County
Solar
200 MWIn study Livingston, MIMISO Sep 2022target 2025
Solar project J1241, Jefferson County
Solar
200 MWAgreement signed Jefferson, ILMISO Apr 2019target 2024
Solar project 385, Lawrence County
Solar
200 MWAgreement signed Lawrence, ALSoutheast Aug 2019target 2026
Solar project J2806, Warren County
Solar
200 MWIn study Warren, MOMISO Sep 2022target 2026
Solar project AH1-150, Lee County
Solar · Steward Creek Solar, LLC
200 MWIn study Lee, ILPJM Feb 2025target 2025
Solar project J3725, Louisa County
Solar
200 MWIn study Louisa, IAMISO Apr 2024target 2028
Solar project J1943, Columbia County
Solar
200 MWIn study Columbia, WIMISO Aug 2021target 2024
Solar project J1664, St. Clair County
Solar
200 MWAgreement signed St. Clair, MIMISO Jun 2020target 2026
SR Bartown frmly Jefferson
Solar
200 MWIn study Jefferson, GASoutheast Dec 2024target 2029
Solar project 7, Grant County
Solar
200 MWIn study Grant, WAWest Sep 2020
Solar project J1215, Arkansas County
Solar
200 MWAgreement signed Arkansas, ARMISO Apr 2019target 2024
Solar project GEN-2019-016, Polk County
Solar
200 MWAgreement signed Polk, MOSPP Apr 2019target 2029
Solar project J1588, Cass County
Solar
200 MWIn study Cass, NDMISO Apr 2024target 2026
Solar project J934, Crittenden County
Solar
200 MWUnder construction Crittenden, ARMISO Jun 20172024
Solar project J3811, Clay County
Solar
200 MWIn study Clay, ILMISO Apr 2024target 2028
Solar project AI1-103, Champaign County
Solar
200 MWIn study Champaign, OHPJM Aug 2022target 2029
Solar project J1325, Rock County
Solar
200 MWUnder construction Rock, MNMISO Apr 2019target 2025
Solar project GEN-2024-154, Beckham County
Solar
200 MWIn study Beckham, OKSPP Mar 2025target 2029
Solar project J3090, Crittenden County
Solar
200 MWIn study Crittenden, ARMISO Sep 2022target 2025
Solar project J2351, Clay County
Solar
200 MWIn study Clay, ARMISO Sep 2022target 2026
Moss Creek Solar
Solar
200 MWAgreement signed Pulaski, INPJM Mar 2020target 2027
Solar project J3852, Tuscola County
Solar
200 MWIn study Tuscola, MIMISO Dec 2024target 2030
Solar project J2374, Sanilac County
Solar
200 MWIn study Sanilac, MIMISO Sep 2022target 2025
Solar project J1559, Conway County
Solar
200 MWUnder construction Conway, ARMISO Jun 2020target 2026
Solar project J1605, Sherburne County
Solar
200 MWIn study Sherburne, MNMISO Jun 2020target 2026
Page 15 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)