United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Projects with signed interconnection agreements in the USA — page 14

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,141423.2 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,141 requests · page 14 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Black & Gold Energy Storage
Battery storage · Black & Gold Energy Storage, LLC
204 MWAgreement signed Menard, TXERCOT Jul 2022target 2027
Diamondback solar
Solar · Diamondback Solar, LLC
204 MWAgreement signed Starr, TXERCOT Sep 2018target 2027
Seahawk Storage
Battery storage
204 MWAgreement signed Santa Cruz, CACAISO Apr 2021target 2029
Cougar Storage
Battery storage
204 MWAgreement signed Merced, CACAISO Apr 2021target 2030
Apache Storage
Battery storage
204 MWAgreement signed Fresno, CACAISO Apr 2021target 2029
Kingsroad Hybrid Solar
Solar + storage
204 MWAgreement signed Kern, CACAISO Apr 2019target 2028
Barton Branch IA
Battery storage · Barton Branch IA LLC
204 MWAgreement signed Robertson, TXERCOT Mar 2021target 2026
Tidwell Prairie II Batt
Battery storage · TIDWELL PRAIRIE II LLC
204 MWAgreement signed Robertson, TXERCOT Mar 2021target 2026
Fewell Solar
Solar · Fewell Solar LLC
204 MWAgreement signed Limestone, TXERCOT Aug 2021target 2027
Glasgow Solar
Solar + storage · Glasgow Solar LLC
204 MWAgreement signed Navarro, TXERCOT Feb 2022target 2027
Solar project GEN-2018-057, Sedgwick County
Solar
203 MWAgreement signed Sedgwick, KSSPP May 2018target 2030
Nockenut Springs Solar 2
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Nockenut Springs Solar 1
Solar · Pecan Springs Energy, LLC
203 MWAgreement signed Guadalupe, TXERCOT Sep 2020target 2029
Callisto II Energy Center
Battery storage · Callisto II Energy Center LLC
203 MWAgreement signed Harris, TXERCOT Oct 2021target 2026
Brookview Road BESS
Battery storage · Brookview Reliability Project LLC
203 MWAgreement signed Harris, TXERCOT Apr 2024target 2028
Big Star Solar
Solar · RWE Solar Development, LLC
203 MWAgreement signed Bastrop, TXERCOT Aug 2019target 2026
OCI Cobb Creek Solar
Solar + storage · Hillsboro Solar Project LLC
203 MWAgreement signed Hill, TXERCOT Nov 2022target 2027
Little Bear 4
Solar + storage
203 MWAgreement signed Fresno, CACAISO Apr 20152020
Bigway Solar I
Solar · NextEra Energy Interconnection Holdings, LLC
203 MWAgreement signed King, TXERCOT Jan 2024target 2028
Bigway Solar II
Solar · NextEra Energy Interconnection Holdings, LLC
203 MWAgreement signed King, TXERCOT Dec 2023target 2028
Nazareth Solar
Solar · TX Nazareth Solar, LLC
203 MWAgreement signed Castro, TXERCOT Jun 2014target 2027
Samson Solar 2
Solar · Samson Solar Energy II LLC
203 MWAgreement signed Lamar, TXERCOT Jan 2020target 2026
Wolf Spring Storage
Solar + storage · Wolf Spring Solar, LLC
203 MWAgreement signed Dickens, TXERCOT Dec 2022target 2028
Aramis Power Plant
Solar + storage
203 MWAgreement signed Alameda, CACAISO May 2017target 2026
Crowded Star I BESS
Solar + storage · Jones City Solar II, LLC
203 MWAgreement signed Jones, TXERCOT Aug 2023target 2027
Trenno BESS
Battery storage · JSB1, LLC
203 MWAgreement signed Johnson, TXERCOT Feb 2024target 2027
Las Camas 3
Solar + storage
203 MWAgreement signed Merced, CACAISO Apr 2018target 2027
Las Camas 1
Solar + storage
203 MWAgreement signed Merced, CACAISO May 2017target 2027
Erin Solar
Solar · Erin Solar LLC
203 MWAgreement signed Wharton, TXERCOT Jul 2020target 2028
Inertia Solar
Solar · Inertia Solar Project, LLC
202 MWAgreement signed Haskell, TXERCOT Feb 2021target 2029
Willow Beach Wind
Onshore wind · Capital Wind, LLC
202 MWAgreement signed Brazoria, TXERCOT Oct 2023target 2027
Bottom Grass BESS
Solar + storage · Bottom Grass Solar Project, LLC
202 MWAgreement signed Colorado, TXERCOT Nov 2020target 2028
Cherrywood Solar I
Solar
202 MWAgreement signed Caroline, MDPJM Feb 2016target 2026
Onshore wind project GEN-2016-004, Oliver County
Onshore wind
202 MWAgreement signed Oliver, NDSPP Mar 2016target 2027
Dodd Solar I
Solar · Forest Grove Solar LLC
202 MWAgreement signed Henderson, TXERCOT Jun 2021target 2028
Donegal Solar
Solar · HE-Cottonwood Solar LLC
202 MWAgreement signed Dickens, TXERCOT Oct 2020target 2028
Soda Lake Solar 2 SLF
Solar + storage · Crane II Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Sep 2020target 2027
Goldeneye BESS
Battery storage · Black Mountain Energy Storage II
202 MWAgreement signed Bell, TXERCOT Jun 2022target 2028
Solar project GEN-2018-132, Pierce County
Solar
202 MWAgreement signed Pierce, NESPP Nov 2018target 2026
Solar + storage project GEN-2020-020, Mccurtain County
Solar + storage
202 MWAgreement signed Mccurtain, OKSPP Apr 2020target 2027
Onshore wind project GEN-2017-004, Cloud County
Onshore wind
202 MWAgreement signed Cloud, KSSPP Apr 2017target 2027
Stoneridge Solar
Solar · Stoneridge Solar, LLC
202 MWAgreement signed Milam, TXERCOT Oct 2021target 2026
Solar project GEN-2017-226, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Mesteno Wind
Onshore wind · Mesteno Windpower, LLC
202 MWAgreement signed Starr, TXERCOT Dec 2014target 2025
OCI Cobb Creek ESS
Solar + storage · Hillsboro Solar Project LLC
202 MWAgreement signed Hill, TXERCOT Dec 2022target 2027
Battery storage project GEN-2017-227, Sedgwick County
Battery storage
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2030
Solar project GEN-2017-220, Sedgwick County
Solar
202 MWAgreement signed Sedgwick, KSSPP Nov 2017target 2026
Thomas Cameron BESS
Battery storage · Thomas Cameron BESS LLC
202 MWAgreement signed Lampasas, TXERCOT Jun 2023target 2027
Corvus Solar
Solar · Corvus Solar, LLC
202 MWAgreement signed Webb, TXERCOT Feb 2024target 2028
Tri-X Solar 1 SLF
Solar + storage · Crane I Solar Electric, LLC
202 MWAgreement signed Crane, TXERCOT Nov 2016target 2027
Page 14 of 43

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)