Withdrawn queue requests in the USA (2021 requests) โ€” page 13

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,149339.1 GW
Active in queue227.7 GW896 requests
Agreement signed73.3 GW270 requests
Withdrawn2,149339.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,149 requests ยท page 13 of 43
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J2096, Terrebonne Parish County
Solar
180 MWWithdrawn / abandoned Terrebonne Parish, LAMISO Aug 2021target 2024
Bobcat
Battery storage
179 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Bulldog Storage
Battery storage
178 MWWithdrawn / abandoned Fresno, CACAISO Apr 2021target 2025
Solar project AH1-232, Winnebago County
Solar
175 MWWithdrawn / abandoned Winnebago, ILPJM Sep 2021target 2025
Solar project AG2-261, Greensville County
Solar
175 MWWithdrawn / abandoned Greensville, VAPJM Mar 2021target 2025
Onshore wind project J1978, Pocahontas County
Onshore wind
175 MWWithdrawn / abandoned Pocahontas, IAMISO Aug 2021target 2025
Crystal Storage Project
Battery storage ยท Hanwha Q CELLS USA
175 MWWithdrawn / abandoned Seneca, NYNYISO Nov 2021
Yorktown
Solar + storage
175 MWWithdrawn / abandoned Kings, CACAISO Apr 2021target 2029
BRP Volga BESS
Battery storage ยท BRP Volga BESS LLC
175 MWWithdrawn / abandoned ERCOT Dec 2021target 2027
Emerald Solar and Storage
Solar ยท Hanwha Q CELLS USA
174 MWWithdrawn / abandoned Genesee, NYNYISO Sep 2021
Garnet Solar and Storage
Solar ยท Hanwha Q CELLS USA
174 MWWithdrawn / abandoned Orleans, NYNYISO Sep 2021
Lopez BESS
Battery storage
172 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2021target 2033
Solar project J2060, Tippecanoe County
Solar
170 MWWithdrawn / abandoned Tippecanoe, INMISO Aug 2021target 2025
Battery Storage
Battery storage
170 MWWithdrawn / abandoned Providence, RIISO-NE Dec 2021target 2024
Solar + storage project GI-2021-28, Alamosa County
Solar + storage
170 MWWithdrawn / abandoned Alamosa, COWest Oct 2021target 2024
Onshore wind project G0718, Lewis County
Onshore wind
170 MWWithdrawn / abandoned Lewis, WAWest Dec 2021target 2027
Solar + storage project 10, Sacramento County
Solar + storage
170 MWWithdrawn / abandoned Sacramento, CAWest Mar 2021target 2028
Solar + storage project J2274, Lincoln County
Solar + storage
170 MWWithdrawn / abandoned Lincoln, MOMISO Jul 2021target 2024
Solar project 480, Colbert County
Solar
170 MWWithdrawn / abandoned Colbert, ALSoutheast Aug 2021
Wren Storage
Other ยท Wren Storage, LLC
170 MWWithdrawn / abandoned Willacy, TXERCOT Jan 2021target 2024
Battery storage project 125, Lewis County
Battery storage
170 MWWithdrawn / abandoned Lewis, WAWest Aug 2021target 2026
Flag City Storage SLF
Battery storage ยท Flag City Solar Project, LLC
169 MWWithdrawn / abandoned Jackson, TXERCOT Nov 2021target 2027
Solar project AH1-609, Richland County
Solar
168 MWWithdrawn / abandoned Richland, OHPJM Sep 2021target 2025
Solar + storage project Q431, Yuma County
Solar + storage
168 MWWithdrawn / abandoned Yuma, AZWest Sep 2021target 2023
Brunswick Energy Storage
Battery storage ยท East Coast Power LLC
165 MWWithdrawn / abandoned Union, NJNYISO Sep 2021
Bowhead Solar
Solar ยท Baffin Bay Solar, LLC
165 MWWithdrawn / abandoned Kleberg, TXERCOT Nov 2021target 2026
Solar + storage project GEN-2021-086, Howard County
Solar + storage
165 MWWithdrawn / abandoned Howard, ARSPP Apr 2021target 2027
Solar project IC-946, Macon County
Solar
165 MWWithdrawn / abandoned Macon, GASoutheast Apr 2021
Solar project 187960, Darlington County
Solar ยท Duke Energy Progress, LLC
165 MWWithdrawn / abandoned Darlington, SCSoutheast Jul 2021
Solar + storage project AH1-540, Ogle County
Solar + storage ยท Golden Harvest Energy, LLC
165 MWWithdrawn / abandoned Ogle, ILPJM Sep 2021target 2025
Harmony Storage 1
Battery storage
165 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2021target 2025
Slate Mountain Solar
Solar + storage
165 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2027
Lago Domingo Solar
Solar + storage
165 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Solar project J1687, Decatur County
Solar
160 MWWithdrawn / abandoned Decatur, INMISO Dec 2021target 2026
Battery Storage
Battery storage
160 MWWithdrawn / abandoned New Haven, CTISO-NE Dec 2021target 2024
Solar project AH1-273, Brown County
Solar
160 MWWithdrawn / abandoned Brown, OHPJM Sep 2021target 2025
Solar project AH1-623, Louisa County
Solar
160 MWWithdrawn / abandoned Louisa, VAPJM Sep 2021target 2025
Solar project IC-984, Mobile County
Solar
160 MWWithdrawn / abandoned Mobile, ALSoutheast Sep 2021
Wind + storage project GEN-2021-098, Dewey County
Wind + storage
160 MWWithdrawn / abandoned Dewey, OKSPP May 2021target 2026
Solar + storage project C1-18, Tooele County
Solar + storage
160 MWWithdrawn / abandoned Tooele, UTWest May 2021target 2025
Solar project AH1-548, Huntington County
Solar
160 MWWithdrawn / abandoned Huntington, INPJM Sep 2021target 2024
Solar project 184484, Marlboro County
Solar ยท Masked
160 MWWithdrawn / abandoned Marlboro, SCSoutheast Jul 2021
Solar + storage project GEN-2021-078, Finney County
Solar + storage
160 MWWithdrawn / abandoned Finney, KSSPP Apr 2021target 2028
Dupont Storage
Battery storage
159 MWWithdrawn / abandoned Ventura, CACAISO Apr 2021target 2025
Lenny Storage
Battery storage
159 MWWithdrawn / abandoned Alameda, CACAISO Apr 2021target 2025
Bernardo Energy Storage
Battery storage
157 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Old Steel Bridge BESS
Battery storage
157 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2025
Solar + storage project G0667, Yakima County
Solar + storage
156 MWWithdrawn / abandoned Yakima, WAWest Jan 2021target 2024
Solar project 478, Bledsoe County
Solar
155 MWWithdrawn / abandoned Bledsoe, TNSoutheast Sep 2021
Legacy
Solar + storage
155 MWWithdrawn / abandoned Kern, CACAISO Apr 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)