Solar + storage project 10, Sacramento County

Solar + storage project 10, Sacramento County is a 170 MW solar + storage request withdrawn in the West interconnection queue, in Sacramento County, California, connecting to Sacramento Municipal Utility District.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
10
Grid region
West (non-ISO utilities)
Utility / transmission owner
Sacramento Municipal Utility District
Connection point (POI)
Cordova 230kV Substation
Location
Sacramento County, California
Technology
Solar: 170 MW Β· Battery
Total requested
170 MW
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
16 March 2021
Proposed online date
January 2028

Location

Marker shows the centre of Sacramento County; the queue data does not give exact sites.