SOLAR + STORAGE · WEST

Solar + storage project 12, Sacramento County

Solar + storage project 12, Sacramento County is a 250 MW solar + storage request in interconnection study in the West interconnection queue, in Sacramento County, California, connecting to Sacramento Municipal Utility District.

Queue statusIn planning
  1. PlanningQueued May 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
12
Grid region
West (non-ISO utilities)
Utility / transmission owner
Sacramento Municipal Utility District
Connection point (POI)
Q3 new switching station near Cordova 230kV Substation
Location
Sacramento County, California
Technology
Solar: 250 MW · Battery
Total requested
250 MW
Study phase
Facility Study
Queue status
Active
Entered queue
20 May 2021
Proposed online date
December 2028

Location

Marker shows the centre of Sacramento County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Sacramento County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem