United States › Grid › Interconnection queues › California
BATTERY STORAGE · WESTBattery storage project 16, Sacramento County
Battery storage project 16, Sacramento County is a 204 MW battery storage request in interconnection study in the West interconnection queue, in Sacramento County, California, connecting to Sacramento Municipal Utility District.
- PlanningQueued Jan 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 16
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Sacramento Municipal Utility District
- Connection point (POI)
- New switching station near Campbells Soup 230kV Substation
- Location
- Sacramento County, California
- Technology
- Battery: 204 MW
- Total requested
- 204 MW
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 21 January 2022
- Proposed online date
- November 2027
Location
Marker shows the centre of Sacramento County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Sacramento County
- Solar + storage project 20, Sacramento CountySolar + storage · 550 MW · in study
- Other project SC1Q31, Sacramento CountyOther · 400 MW · in study
- Solar + storage project 8, Sacramento CountySolar + storage · 344 MW · in study
- Solar + storage project 26, Sacramento CountySolar + storage · 275 MW · in study
- Other project SC1Q33, Sacramento CountyOther · 250 MW · in study
- Solar + storage project 12, Sacramento CountySolar + storage · 250 MW · in study
- Solar + storage project 3, Sacramento CountySolar + storage · 250 MW · in study
- Battery storage project SC1Q32, Sacramento CountyBattery storage · 200 MW · in study
- Battery storage project 11, Sacramento CountyBattery storage · 200 MW · in study
- Battery storage project 22, Sacramento CountyBattery storage · 160 MW · in study
- Solar + storage project 30, Sacramento CountySolar + storage · 156 MW · in study
- Battery storage project 27, Sacramento CountyBattery storage · 150 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem