πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

BATTERY STORAGE Β· ERCOT

BRP Volga BESS

BRP Volga BESS is a 175 MW battery storage request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2021 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
24INR0096
Grid region
ERCOT (Texas)
Developer
BRP Volga BESS LLC
Connection point (POI)
138 kV Seagoville Switch Substation (#2434; ONCOR)
Technology
Battery: 175 MW
Total requested
175 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
20 December 2021
Proposed online date
December 2027
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem