United States βΊ Grid βΊ Interconnection queues βΊ Indiana
SOLAR Β· PJMSolar project AH1-548, Huntington County
Solar project AH1-548, Huntington County is a 160 MW solar request withdrawn in the PJM interconnection queue, in Huntington County, Indiana, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-548
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Sorenson 345 kV
- Location
- Huntington County, Indiana
- Technology
- Solar: 160 MW
- Total requested
- 160 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 10 September 2021
- Proposed online date
- December 2024
- Withdrawn
- December 2024
Location
Marker shows the centre of Huntington County; the queue data does not give exact sites.
Other requests in Huntington County
- Maple SolarSolar Β· 35.0 MW Β· agreement signed
- Battery storage project AI1-022, Huntington CountyBattery storage Β· 450 MW Β· in study
- Solar + storage project AH2-413, Huntington CountySolar + storage Β· 365 MW Β· in study
- Battery storage project AH2-414, Huntington CountyBattery storage Β· 350 MW Β· in study
- Onshore wind project AI1-003, Huntington CountyOnshore wind Β· 170 MW Β· in study
- Solar project AI2-150, Huntington CountySolar Β· 44.4 MW Β· in study
- Solar project AI2-425, Huntington CountySolar Β· 40.0 MW Β· in study
- Solar project AI2-424, Huntington CountySolar Β· 28.0 MW Β· in study
- Bowfin SolarSolar + storage Β· 150 MW Β· suspended
- Solar project AH1-291, Huntington CountySolar Β· 185 MW Β· withdrawn
- Solar project AH1-014, Huntington CountySolar Β· 112 MW Β· withdrawn
- Solar project AF2-094, Huntington CountySolar Β· 40.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem