Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 124 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Yellow Jacket Wind
Onshore wind · RES Americas
200 MWWithdrawn / abandoned ERCOT Dec 2016target 2019
Onshore wind project GEN-2009-018, Hansford County
Onshore wind
200 MWWithdrawn / abandoned Hansford, TXSPP Apr 2009target 2011
Roscoe 5
Onshore wind · Airtricity, Inc
200 MWWithdrawn / abandoned ERCOT Jan 2008target 2013
Solar project J1623, Orange County
Solar
200 MWWithdrawn / abandoned Orange, INMISO Jun 2020target 2024
Coronado Wind Energy Project
Onshore wind · Airtricity, Inc
200 MWWithdrawn / abandoned ERCOT Mar 2006target 2050
Onshore wind project J873, Hardin County
Onshore wind
200 MWWithdrawn / abandoned Hardin, IAMISO Jun 2017target 2021
Sweet Valley Solar
Solar · Sweet Valley Energy Center
200 MWWithdrawn / abandoned Genesee, NYNYISO Dec 2022
Battery storage project J2204, St. Clair County
Battery storage
200 MWWithdrawn / abandoned St. Clair, ILMISO Oct 2021target 2024
Battery storage project 106, Lewis County
Battery storage
200 MWWithdrawn / abandoned Lewis, WAWest Apr 2021target 2023
Solar project 463, Chickasaw County
Solar
200 MWWithdrawn / abandoned Chickasaw, MSSoutheast Dec 2020
Solar + storage project AE1-135, Greensville County
Solar + storage
200 MWWithdrawn / abandoned Greensville, VAPJM Sep 2018target 2019
Solar project 49, Pima County
Solar
200 MWWithdrawn / abandoned Pima, AZWest Sep 2016target 2019
Solar project AH1-635, Champaign County
Solar
200 MWWithdrawn / abandoned Champaign, OHPJM Sep 2021target 2024
Battery storage project GEN-2023-019, Tillman County
Battery storage
200 MWWithdrawn / abandoned Tillman, OKSPP Oct 2023target 2026
Onshore wind project G999, Clinton County
Onshore wind
200 MWWithdrawn / abandoned Clinton, INMISO Apr 2008target 2012
Bravepost Solar
Solar · Recurrent Energy
200 MWWithdrawn / abandoned Tom Green, TXERCOT Feb 2018target 2024
Solar project 500, Mccracken County
Solar
200 MWWithdrawn / abandoned Mccracken, KYSoutheast May 2022
St Lawrence Data and Agricultural Center
Other · PetaWatt Holdings, Inc.
200 MWWithdrawn / abandoned St. Lawrence, NYNYISO Jun 2021
Solar project Q67, Maricopa County
Solar
200 MWWithdrawn / abandoned Maricopa, AZWest Jun 2009target 2015
Battery storage project 1175, Salt Lake County
Battery storage
200 MWWithdrawn / abandoned Salt Lake, UTWest Oct 2019target 2024
Battery storage project AG2-331, Decatur County
Battery storage · Cobia Solar LLC
200 MWWithdrawn / abandoned Decatur, INPJM Feb 2025target 2024
Lukrich Energy Center
Battery storage
200 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Solar project GEN-2022-025, Decatur County
Solar
200 MWWithdrawn / abandoned Decatur, KSSPP Jun 20222025
Battery storage project IC-1041, Fulton County
Battery storage
200 MWWithdrawn / abandoned Fulton, GASoutheast Jul 2022
Onshore wind project J135, Buffalo County
Onshore wind
200 MWWithdrawn / abandoned Buffalo, WIMISO Feb 2008target 2011
Onshore wind project GEN-2008-046, Murray County
Onshore wind
200 MWWithdrawn / abandoned Murray, OKSPP May 2008target 2010
Onshore wind project U4-010, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, ILPJM Nov 2008target 2012
Onshore wind project GI-0726, Barnes County
Onshore wind
200 MWWithdrawn / abandoned Barnes, NDWest Dec 2007target 2010
Agate Storage Project
Battery storage · Hanwha Q Cells USA
200 MWWithdrawn / abandoned Dutchess, NYNYISO Nov 2021
Battery storage project AI2-023, Lake County
Battery storage
200 MWWithdrawn / abandoned Lake, INPJM Dec 2022target 2028
Onshore wind project GEN-2007-036, Ford County
Onshore wind
200 MWWithdrawn / abandoned Ford, KSSPP Sep 2007target 2012
Onshore wind project G959, Goodhue County
Onshore wind
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2011target 2010
Onshore wind project G746, Fillmore County
Onshore wind
200 MWWithdrawn / abandoned Fillmore, MNMISO Feb 2007target 2010
Solar project IC-870, Lauderdale County
Solar
200 MWWithdrawn / abandoned Lauderdale, MSSoutheast May 2020
Onshore wind project G0312, Klickitat County
Onshore wind
200 MWWithdrawn / abandoned Klickitat, WAWest Jan 2008target 2011
Coal project GI-0402, Grant County
Coal
200 MWWithdrawn / abandoned Grant, SDWest Apr 2004target 2013
Solar project AG1-421, Augusta County
Solar · Leeward Renewable Energy Development, LLC
200 MWWithdrawn / abandoned Augusta, VAPJM Sep 2020target 2023
Onshore wind project Q07, Navajo County
Onshore wind
200 MWWithdrawn / abandoned Navajo, AZWest Oct 2008target 2013
Solar project AF2-210, Pickaway County
Solar
200 MWWithdrawn / abandoned Pickaway, OHPJM Mar 2020target 2023
Onshore wind project G445, Howard County
Onshore wind
200 MWWithdrawn / abandoned Howard, IAMISO Aug 2004target 2005
Battery storage project 24-247, Columbia County
Battery storage
200 MWWithdrawn / abandoned Columbia, ORWest May 2024target 2027
Solar project 454, Clay County
Solar
200 MWWithdrawn / abandoned Clay, MSSoutheast Aug 2020
Solar + storage project GEN-2023-083, Banner County
Solar + storage
200 MWWithdrawn / abandoned Banner, NESPP Oct 2023target 2027
Onshore wind project J528, Adair County
Onshore wind
200 MWWithdrawn / abandoned Adair, IAMISO Nov 2015target 2020
Solar project Q241, Yavapai County
Solar
200 MWWithdrawn / abandoned Yavapai, AZWest Mar 2016target 2019
Fitch Solar
Solar
200 MWWithdrawn / abandoned Fauquier, VAPJM Jul 2018target 2025
Solar project AG1-321, Livingston County
Solar · CPV Prairie Dock Solar, LLC
200 MWWithdrawn / abandoned Livingston, ILPJM Sep 2020target 2023
Murray Wind Ranch
Onshore wind · Austin Energy
200 MWWithdrawn / abandoned ERCOT Jul 2009target 2014
Onshore wind project J579, Allegan County
Onshore wind
200 MWWithdrawn / abandoned Allegan, MIMISO Jun 2017target 2018
Solar + storage project IC-895, Hale County
Solar + storage
200 MWWithdrawn / abandoned Hale, ALSoutheast Jul 2020
Page 124 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)