United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

SOLAR Β· SOUTHEAST

Solar project IC-870, Lauderdale County

Solar project IC-870, Lauderdale County is a 200 MW solar request withdrawn in the Southeast interconnection queue, in Lauderdale County, Mississippi, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2020 (completed)
  2. Withdrawn / abandonedAug 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-870
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Vimille Substation 230 kV Bus
Location
Lauderdale County, Mississippi
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
28 May 2020
Withdrawn
August 2021

Location

Marker shows the centre of Lauderdale County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Lauderdale County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem