United States › Grid › Interconnection queues › Mississippi
SOLAR · SOUTHEASTMeridian 55 MW
Meridian 55 MW is a 55.0 MW solar request built and operating in the Southeast interconnection queue, in Lauderdale County, Mississippi, connecting to Southern Company.
Request details
- Queue ID
- IC-459
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Location
- Lauderdale County, Mississippi
- Technology
- Solar: 55.0 MW
- Total requested
- 55.0 MW
- Study phase
- Operational
- Queue status
- Operational
- Agreement signed
- 19 June 2018
- Came online
- February 2020
Location
Marker shows the centre of Lauderdale County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Lauderdale County
- Gas project IC-124, Lauderdale CountyGas · 626 MW · withdrawn
- Gas project IC-123, Lauderdale CountyGas · 615 MW · withdrawn
- Solar project IC-870, Lauderdale CountySolar · 200 MW · withdrawn
- Solar project IC-460, Lauderdale CountySolar · 50.0 MW · withdrawn
- Solar project IC-404, Lauderdale CountySolar · 49.4 MW · withdrawn
- Other project 265, Lauderdale CountyOther · 40.0 MW · withdrawn
- Other project 264, Lauderdale CountyOther · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem