ONSHORE WIND Β· SPP

Onshore wind project GEN-2008-046, Murray County

Onshore wind project GEN-2008-046, Murray County is a 200 MW onshore wind request withdrawn in the SPP interconnection queue, in Murray County, Oklahoma, connecting to OGE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2008 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2008-046
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Sunnyside 345kV
Location
Murray County, Oklahoma
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
16 May 2008
Proposed online date
December 2010
Withdrawn
May 2013

Location

Marker shows the centre of Murray County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Murray County