Requests shown1,836452.0 GW
Active in queue452.0 GW1,836 requests
Agreement signed4,701 MW27 requests
Withdrawn47497.1 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,836 requests ยท page 12 of 37
ProjectCapacityStatusLocationRegionQueuedOnline
Wake Wind Energy
Onshore wind ยท WAKE WIND ENERGY
251 MWIn study Crosby, TXERCOT Apr 2025target 2027
Replacing 244 MW of Solar with Nuclear; Duane Arnold
Nuclear
251 MWIn study Linn, IAMISO Aug 2025target 2029
Alkali Creek Wind 2
Onshore wind ยท Alkali Creek Wind, LLC
250 MWIn study Fisher, TXERCOT Dec 2025target 2028
Ca-CO-250B
Battery storage
250 MWIn study El Paso, TXWest Jun 2025target 2029
Other project SC1Q33, Sacramento County
Other
250 MWIn study Sacramento, CAWest Jul 2025target 2030
Battery storage project J4167, Allegan County
Battery storage
250 MWIn study Allegan, MIMISO Sep 2025target 2030
Battery storage project GEN-2024-171, Tulsa County
Battery storage
250 MWIn study Tulsa, OKSPP Mar 2025target 2028
Other project Q593, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Solar project GEN-2024-140, Douglas County
Solar
250 MWIn study Douglas, NESPP Mar 2025target 2033
Battery storage project J3883, Crawford County
Battery storage
250 MWIn study Crawford, ILMISO Feb 2025target 2030
Battery storage project 25-IC-1312, Coweta County
Battery storage
250 MWIn study Coweta, GASoutheast Apr 2025target 2028
Battery storage project J4198, Christian County
Battery storage
250 MWIn study Christian, ILMISO Sep 2025target 2030
Other project Q595, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Solar project GEN-2024-232, Houston County
Solar
250 MWIn study Houston, TXSPP Mar 2025target 2029
Other project Q594, Pinal County
Other
250 MWIn study Pinal, AZWest May 2025target 2029
Battery storage project J4153, Grant County
Battery storage
250 MWIn study Grant, SDMISO Oct 2025target 2030
Battery storage project GEN-2024-242, Carter County
Battery storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Other project Q618, Pima County
Other
250 MWIn study Pima, AZWest May 2025target 2030
Battery storage project J4089, Freeborn County
Battery storage
250 MWIn study Freeborn, MNMISO Oct 2025target 2029
Solar + storage project GEN-2024-337, Carter County
Solar + storage
250 MWIn study Carter, OKSPP Mar 2025target 2029
Battery storage project 977301, Gaston County
Battery storage
250 MWIn study Gaston, NCSoutheast Jun 2025
Solar + storage project IA-PNM-2025-04, Bernalillo County
Solar + storage
250 MWIn study Bernalillo, NMWest Mar 2025target 2028
Battery storage project CS25-08, Spokane County
Battery storage
250 MWIn study Spokane, WAWest Apr 2025target 2029
Onshore wind project GEN-2024-291, Pittsburg County
Onshore wind
250 MWIn study Pittsburg, OKSPP Mar 2025target 2030
Battery storage project J4058, Huron County
Battery storage
250 MWIn study Huron, MIMISO Aug 2025target 2028
Battery storage project 25-IC-1313, Bartow County
Battery storage
250 MWIn study Bartow, GASoutheast Apr 2025target 2028
Battery storage project GEN-2024-367, Comanche County
Battery storage
250 MWIn study Comanche, OKSPP Mar 2025target 2028
Onshore wind project GEN-2024-135, Woods County
Onshore wind
250 MWIn study Woods, OKSPP Mar 2025target 2031
Battery storage project J4026, Lenawee County
Battery storage
250 MWIn study Lenawee, MIMISO May 2025target 2029
Solar project GEN-2024-153, Randall County
Solar
250 MWIn study Randall, TXSPP Mar 2025target 2029
Battery storage project 25-00431, Storey County
Battery storage
250 MWIn study Storey, NVWest Jul 2025target 2029
Battery storage project GEN-2024-368, Gray County
Battery storage
250 MWIn study Gray, TXSPP Mar 2025target 2028
Other project Q598, Maricopa County
Other
250 MWIn study Maricopa, AZWest May 2025target 2029
Solar project J4066, Isabella County
Solar
250 MWIn study Isabella, MIMISO Sep 2025target 2030
Onshore wind project GEN-2024-145, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Other project Q610, San Juan County
Other
250 MWIn study San Juan, NMWest May 2025target 2029
Onshore wind project GEN-2024-143, Dallam County
Onshore wind
250 MWIn study Dallam, TXSPP Mar 2025target 2032
Onshore wind project GEN-2024-134, Woods County
Onshore wind
250 MWIn study Woods, OKSPP Mar 2025target 2031
Solar project 25-IC-1326, Jasper County
Solar
250 MWIn study Jasper, GASoutheast Apr 2025target 2030
Battery storage project ERAS-2025-027, Yoakum County
Battery storage
250 MWIn study Yoakum, TXSPP Oct 2025target 2028
Gas project ERAS-2025-034, Jasper County
Gas
250 MWIn study Jasper, MOSPP Sep 2025target 2030
Battery storage project 25RSC-005, Mccracken County
Battery storage
250 MWIn study Mccracken, KYSoutheast Jul 2025target 2030
Battery storage project J3977, Sanilac County
Battery storage
250 MWIn study Sanilac, MIMISO Mar 2025target 2029
Onshore wind project GEN-2024-285, Clark County
Onshore wind
250 MWIn study Clark, SDSPP Mar 2025target 2030
Solar project J4152, Redwood County
Solar
250 MWIn study Redwood, MNMISO Oct 2025target 2028
Onshore wind project IA-PNM-2025-18, Torrance County
Onshore wind
250 MWIn study Torrance, NMWest Mar 2025target 2028
Battery storage project 977286, Stokes County
Battery storage
250 MWIn study Stokes, NCSoutheast Jun 2025
Battery storage project AG2-360, Smyth County
Battery storage ยท Laurel Creek Energy Storage LLC
250 MWIn study Smyth, VAPJM Feb 2025target 2024
Battery storage project 308, Berkeley County
Battery storage
250 MWIn study Berkeley, SCSoutheast May 2025target 2028
Battery storage project GEN-2024-369, Grady County
Battery storage
250 MWIn study Grady, OKSPP Mar 2025target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)