SOLAR · SPPSolar project GEN-2024-140, Douglas County
Solar project GEN-2024-140, Douglas County is a 250 MW solar request in interconnection study in the SPP interconnection queue, in Douglas County, Nebraska, connecting to NPPD.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2033 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-140
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Antelope - Hoskins 345 kV line
- Location
- Douglas County, Nebraska
- Technology
- Solar: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- December 2033
Location
Marker shows the centre of Douglas County; the queue data does not give exact sites.
Other requests in Douglas County
- Battery storage project GEN-2017-198, Douglas CountyBattery storage · 11.6 MW · agreement signed
- Battery storage project GEN-2024-372, Douglas CountyBattery storage · 250 MW · in study
- Battery storage project GEN-2021-039, Douglas CountyBattery storage · 100 MW · in study
- Other project GEN-2025-SR20, Douglas CountyOther · 100 MW · in study
- Battery storage project GEN-2018-037, Douglas CountyBattery storage · 100 MW · suspended
- Gas project GEN-2020-043, Douglas CountyGas · 56.5 MW · built
- Gas project GEN-2020-044, Douglas CountyGas · 56.5 MW · built
- Gas project GEN-2020-045, Douglas CountyGas · 56.5 MW · built
- Battery storage project GEN-2024-179, Douglas CountyBattery storage · 199 MW · withdrawn
- Battery storage project GEN-2024-188, Douglas CountyBattery storage · 199 MW · withdrawn
- Gas project GEN-2020-048, Douglas CountyGas · 56.5 MW · withdrawn
- Gas project GEN-2020-049, Douglas CountyGas · 56.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem