United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
GAS Β· SPPGas project GEN-2020-048, Douglas County
Gas project GEN-2020-048, Douglas County is a 56.5 MW gas request withdrawn in the SPP interconnection queue, in Douglas County, Nebraska, connecting to OPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2020 (completed)
- Withdrawn / abandonedSep 2022 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingMay 2023 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2020-048
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Substation 1211; 161kV
- Location
- Douglas County, Nebraska
- Technology
- Gas: 56.5 MW
- Total requested
- 56.5 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 29 April 2020
- Proposed online date
- May 2023
- Came online
- May 2023
- Withdrawn
- September 2022
Location
Marker shows the centre of Douglas County; the queue data does not give exact sites.
Other requests in Douglas County
- Battery storage project GEN-2017-198, Douglas CountyBattery storage Β· 11.6 MW Β· agreement signed
- Solar project GEN-2024-140, Douglas CountySolar Β· 250 MW Β· in study
- Battery storage project GEN-2024-372, Douglas CountyBattery storage Β· 250 MW Β· in study
- Battery storage project GEN-2021-039, Douglas CountyBattery storage Β· 100 MW Β· in study
- Other project GEN-2025-SR20, Douglas CountyOther Β· 100 MW Β· in study
- Battery storage project GEN-2018-037, Douglas CountyBattery storage Β· 100 MW Β· suspended
- Gas project GEN-2020-043, Douglas CountyGas Β· 56.5 MW Β· built
- Gas project GEN-2020-044, Douglas CountyGas Β· 56.5 MW Β· built
- Gas project GEN-2020-045, Douglas CountyGas Β· 56.5 MW Β· built
- Battery storage project GEN-2024-179, Douglas CountyBattery storage Β· 199 MW Β· withdrawn
- Battery storage project GEN-2024-188, Douglas CountyBattery storage Β· 199 MW Β· withdrawn
- Gas project GEN-2020-049, Douglas CountyGas Β· 56.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem