United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · SPPBattery storage project GEN-2024-368, Gray County
Battery storage project GEN-2024-368, Gray County is a 250 MW battery storage request in interconnection study in the SPP interconnection queue, in Gray County, Texas, connecting to SPS.
Queue statusIn planning
- PlanningQueued Mar 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-368
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Bowers 115 kV Substation
- Location
- Gray County, Texas
- Technology
- Battery: 250 MW
- Total requested
- 250 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 1 March 2025
- Proposed online date
- March 2028
Location
Marker shows the centre of Gray County; the queue data does not give exact sites.
Other requests in Gray County
- Meitner WindOnshore wind · 709 MW · agreement signed
- Meitner SolarSolar · 703 MW · agreement signed
- Meitner 2 WindOnshore wind · 709 MW · in study
- Grandview 5 WOnshore wind · 249 MW · suspended
- Gas project GEN-2012-014, Gray CountyGas · 425 MW · withdrawn
- Onshore wind project GEN-2007-008, Gray CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2016-059, Gray CountyOnshore wind · 300 MW · withdrawn
- Onshore wind project GEN-2007-030, Gray CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project GEN-2007-009, Gray CountyOnshore wind · 200 MW · withdrawn
- Coal project GEN-2007-002, Gray CountyCoal · 160 MW · withdrawn
- Onshore wind project GEN-2002-021, Gray CountyOnshore wind · 160 MW · withdrawn
- Onshore wind project GEN-2008-053, Gray CountyOnshore wind · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem