COAL Β· SPP

Coal project GEN-2007-002, Gray County

Coal project GEN-2007-002, Gray County is a 160 MW coal request withdrawn in the SPP interconnection queue, in Gray County, Texas, connecting to SPS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2007 (completed)
  2. Withdrawn / abandonedJan 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2007-002
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Grapevine 115kV
Location
Gray County, Texas
Technology
Coal: 160 MW
Total requested
160 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
29 January 2007
Proposed online date
September 2009
Withdrawn
January 2012

Location

Marker shows the centre of Gray County; the queue data does not give exact sites.