Onshore wind project GEN-2024-145, Dallam County

Onshore wind project GEN-2024-145, Dallam County is a 250 MW onshore wind request in interconnection study in the SPP interconnection queue, in Dallam County, Texas, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Mar 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2032 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2024-145
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
XIT Interchange 230 kV Substation
Location
Dallam County, Texas
Technology
Wind: 250 MW
Total requested
250 MW
Service type
NRIS and ERIS
Study phase
DISIS STAGE
Queue status
Active
Entered queue
1 March 2025
Proposed online date
December 2032

Location

Marker shows the centre of Dallam County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Dallam County