United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in the USA — page 113

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown6,8521,550.1 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

6,852 requests · page 113 of 138
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project AI1-211, Preston County
Solar + storage
68.0 MWIn study Preston, WVPJM Sep 2022target 2024
Onshore wind project GEN-2025-SR2, Hansford County
Onshore wind
67.2 MWIn study Hansford, TXSPP May 2025target 2028
Onshore wind project G1012, Umatilla County
Onshore wind
67.0 MWIn study Umatilla, ORWest Nov 2023target 2030
Solar project 16-060, Jefferson County
Solar
67.0 MWPaused / redesign Jefferson, ORWest Sep 2016target 2018
Solar + storage project 799, Box Elder County
Solar + storage · Steel Solar, LLC
67.0 MWPaused / redesign Box Elder, UTWest Sep 2016target 2023
Solar project 522, Choctaw County
Solar
67.0 MWIn study Choctaw, MSSoutheast Sep 2022target 2026
Solar project J2177, Tipton County
Solar
67.0 MWIn study Tipton, INMISO Aug 2021target 2024
Other project PP00037, Wayne County
Other
67.0 MWIn study Wayne, NCSoutheast Jul 2025target 2029
Onshore wind project J3976, Fayette County
Onshore wind
66.8 MWIn study Fayette, ILMISO Mar 2025target 2028
Battery storage project AG2-289, Seneca County
Battery storage · Chinchilla Solar LLC
66.6 MWIn study Seneca, OHPJM Feb 2025target 2024
Symank Solar
Solar · BT Symank Solar, LLC
66.6 MWIn study Bosque, TXERCOT Nov 2024target 2027
Solar + storage project AG2-519, Delaware County
Solar + storage · Muncie Solar 1, LLC
66.5 MWIn study Delaware, INPJM Mar 2025target 2024
Julius Solar
Solar · Julius Energy, LLC
66.0 MWIn study Somerset, PAPJM Feb 2025target 2024
Onshore wind project J1998, Franklin County
Onshore wind
66.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Lamar Unit 1 Repower
Gas · La Frontera Holdings, LLC
66.0 MWIn study Lamar, TXERCOT Jun 2022target 2027
Gas project 20211118004, Aiken County
Gas · DESC - Generation
65.9 MWIn study Aiken, SCSoutheast target 2024
Gas project 20211118005, Berkeley County
Gas · DESC - Generation
65.4 MWIn study Berkeley, SCSoutheast target 2026
Other project GEN-2024-231, Richardson County
Other
65.0 MWIn study Richardson, NESPP Mar 2025target 2029
Solar + storage project 433, Stillwater County
Solar + storage
65.0 MWIn study Stillwater, MTWest Sep 2022target 2025
Solar + storage project GI-2022-157, Imperial County
Solar + storage
65.0 MWIn study Imperial, CAWest Sep 2022target 2024
Solar + storage project 434, Stillwater County
Solar + storage
65.0 MWIn study Stillwater, MTWest Sep 2022target 2025
Smith Lake Storage DC
Solar + storage · Smith Lake Solar
65.0 MWIn study Grimes, TXERCOT Mar 2022target 2028
Solar project 915787, Florence County
Solar
65.0 MWIn study Florence, SCSoutheast Sep 2023
Nuclear project 25-IC-1302, Appling County
Nuclear
65.0 MWIn study Appling, GASoutheast Mar 2025target 2031
Solar project 915773, Dillon County
Solar
65.0 MWIn study Dillon, SCSoutheast Sep 2023
Solar project AH2-195, Indiana County
Solar
65.0 MWIn study Indiana, PAPJM Mar 2022target 2027
Solar project AH1-546, Buckingham County
Solar · Mountain Pine Arvonia LLC
65.0 MWIn study Buckingham, VAPJM Feb 2025target 2025
Solar project QF17-068, Jefferson County
Solar
65.0 MWPaused / redesign Jefferson, ORWest Oct 2017target 2019
Other project PP00050, Cumberland County
Other
65.0 MWIn study Cumberland, NCSoutheast Sep 2025target 2029
Demeter Storage
Solar + storage · Demeter Solar, LLC
65.0 MWIn study Caldwell, TXERCOT Aug 2022target 2029
SR Millen
Solar
65.0 MWIn study Jenkins, GASoutheast Jan 2025target 2029
Solar project 963044, Cumberland County
Solar · Duke Energy Progress LLC
65.0 MWIn study Cumberland, NCSoutheast Sep 2024
Gas project 20211118003, Aiken County
Gas · DESC - Generation
64.9 MWIn study Aiken, SCSoutheast target 2024
Solar + storage project AI1-079, Adair County
Solar + storage
64.8 MWIn study Adair, KYPJM Jul 2022target 2026
Solar project J3529, Mahnomen County
Solar
64.0 MWIn study Mahnomen, MNMISO May 2024target 2028
Solar project AI1-147, Dekalb County
Solar
64.0 MWIn study Dekalb, ILPJM Sep 2022target 2026
Replacing 50 MW of Solar with Nuclear; Duane Arnold
Nuclear
64.0 MWIn study Linn, IAMISO Aug 2025target 2029
Solar project 109, Horry County
Solar
64.0 MWIn study Horry, SCSoutheast Jul 2018target 2020
Morrow County Solar II
Solar
64.0 MWPaused / redesign Morrow, OHPJM Sep 2019target 2026
Solar project 917739, Marion County
Solar
63.9 MWIn study Marion, SCSoutheast Sep 2023
Other project PP00029, Marion County
Other
63.9 MWIn study Marion, SCSoutheast Jun 2025target 2027
PRI Solar
Solar · BHER Power Resources, Inc.
63.8 MWIn study Howard, TXERCOT Jul 2025target 2027
Box
Solar
63.4 MWIn study Riverside, CACAISO Apr 2023target 2029
Solar + storage project AG2-424, Larue County
Solar + storage · Magnolia Solar and Grazing Farm LLC
63.3 MWIn study Larue, KYPJM Mar 2025target 2023
Iron Cowboy Storage
Solar + storage · Vaquero II Storage, LLC
63.3 MWIn study San Patricio, TXERCOT Jun 2025target 2028
Little Hill
Battery storage
63.1 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Solar project AG2-411, Somerset County
Solar · Iris Energy LLC
63.0 MWIn study Somerset, PAPJM Mar 2025target 2024
Angus Storage
Battery storage
63.0 MWPaused / redesign Bosque, TXERCOT Nov 2017
Solar project J2029, Marquette County
Solar
62.5 MWIn study Marquette, MIMISO Nov 2021target 2024
Battery storage project AH2-072, Washington County
Battery storage
62.1 MWIn study Washington, VAPJM Jan 2022target 2025
Page 113 of 138

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)