United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in the USA (2019 requests) โ€” page 11

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown589109.2 GW
Active in queue109.2 GW589 requests
Agreement signed64.3 GW347 requests
Withdrawn1,473226.5 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

589 requests ยท page 11 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project Company 185, Clark County
Battery storage
30.0 MWAgreement signed Clark, NVWest Sep 2019target 2023
Onshore wind project J1470, Benton County
Onshore wind
30.0 MWAgreement signed Benton, INMISO Apr 20192020
Gas project G0620, Umatilla County
Gas
27.0 MWIn study Umatilla, ORWest Apr 2019target 2019
Battery storage project J1323, Lagrange County
Battery storage
25.0 MWAgreement signed Lagrange, INMISO Apr 2019target 2025
Knickerbocker Storage
Other ยท Knickerbocker Solar LLC
25.0 MWPaused / redesign Tom Green, TXERCOT Dec 2019target 2028
Gas project J1262, Wayne County
Gas
25.0 MWAgreement signed Wayne, MIMISO Apr 2019target 2022
Dynamo Solar
Solar
24.5 MWAgreement signed Napa, CACAISO Apr 2019target 2027
Solar + storage project J1200, Putnam County
Solar + storage
24.2 MWAgreement signed Putnam, ILMISO Apr 2019target 2024
Wise County Power Repower (CT1, CT2)
Gas ยท Wise County Power Company LLC
21.0 MWAgreement signed Wise, TXERCOT Jul 2019target 2026
Concho Solar I
Solar
20.0 MWPaused / redesign Queen Anne's, MDPJM May 2019target 2024
Momentum Gratz
Battery storage
20.0 MWPaused / redesign Dauphin, PAPJM Jun 2019target 2024
Missouri Avenue Battery Storage Project
Battery storage ยท Calpine Mid-Atlantic Development, LLC
20.0 MWAgreement signed Atlantic, NJPJM Nov 2019target 2028
Mountain Holly
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2027
Hatchery Solar
Solar ยท Hatchery Solar LLC
20.0 MWIn study Livingston, NYNYISO Oct 2019target 2026
Battery storage project J1257, Tangipahoa Parish County
Battery storage
20.0 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Battery storage project J1329, Washtenaw County
Battery storage
20.0 MWUnder construction Washtenaw, MIMISO Apr 2019target 2025
Flat Hill Solar
Solar ยท Flat Hill Solar NY LLC.
20.0 MWIn study Herkimer, NYNYISO May 2019
Calumet BESS
Battery storage
20.0 MWAgreement signed Cook, ILPJM Oct 2019target 2027
Franklin Solar
Solar
20.0 MWAgreement signed Crawford, PAPJM Aug 2019target 2026
Kce NY 10
Battery storage ยท KCE NY 10, LLC
20.0 MWIn study Erie, NYNYISO Mar 2019target 2026
FR-Williamsport
Solar
20.0 MWAgreement signed Franklin, PAPJM Sep 2019target 2025
Rochelle Solar
Solar
20.0 MWAgreement signed Ogle, ILPJM Sep 2019target 2028
HU-Pauls
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Mar 2019target 2027
Kincaid PV
Solar
20.0 MWAgreement signed Christian, ILPJM Oct 2019target 2028
CL-Green Acres
Solar
20.0 MWAgreement signed Clearfield, PAPJM Sep 2019target 2028
Montour 1
Solar
20.0 MWPaused / redesign Columbia, PAPJM Mar 2019target 2025
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Sparkl BESS
Battery storage
20.0 MWPaused / redesign Guadalupe, TXERCOT Dec 2019
Chester Solar Technology Park
Solar
20.0 MWAgreement signed Chesterfield, VAPJM Sep 2019target 2027
Fairway Solar
Solar ยท Fairway Solar NY LLC
20.0 MWIn study St. Lawrence, NYNYISO May 2019target 2028
Solar + storage project J1199, Fulton County
Solar + storage
20.0 MWAgreement signed Fulton, ILMISO Apr 2019target 2023
Fayette Energy Facility
Battery storage
20.0 MWAgreement signed Fayette, PAPJM Oct 2019target 2028
Grassy Knoll Solar
Solar ยท Grassy Knoll Solar NY LLC
20.0 MWIn study Herkimer, NYNYISO Jun 2019target 2028
Ontelaunee Power Generating Plant
Battery storage
20.0 MWAgreement signed Berks, PAPJM Oct 2019target 2029
Dover Solar
Solar
20.0 MWPaused / redesign York, PAPJM Jul 2019target 2026
HU-Logging
Solar
20.0 MWPaused / redesign Huntingdon, PAPJM Feb 2019target 2024
Charles County Solar I
Solar
20.0 MWPaused / redesign Charles, MDPJM Apr 2019target 2028
SunEast Hooversville Solar
Solar
20.0 MWPaused / redesign Somerset, PAPJM Oct 2019target 2026
Hilltop Solar
Solar ยท SunEast Hilltop Solar LLC
20.0 MWIn study Rensselaer, NYNYISO Mar 2019target 2028
Knoxville Solar
Solar
20.0 MWAgreement signed Isle Of Wight, VAPJM Apr 2019target 2027
Knoxville Solar
Solar
20.0 MWAgreement signed Isle Of Wight, VAPJM Mar 2019target 2027
CS Hawthorn Solar
Solar ยท Hawthorn Solar, LLC
20.0 MWIn study Rensselaer, NYNYISO May 2019target 2026
Harrowgate 1
Solar
20.0 MWAgreement signed Chesterfield, VAPJM Mar 2019target 2027
NY13 Solar
Solar ยท Bald Mountain Solar LLC
20.0 MWIn study Washington, NYNYISO May 2019target 2027
SunEast Hooversville Solar
Solar
20.0 MWPaused / redesign Somerset, PAPJM Sep 2019target 2026
Middle Battery Storage
Battery storage
20.0 MWAgreement signed Cape May, NJPJM Nov 2019target 2028
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Dolan Solar
Solar ยท Dolan Solar, LLC
20.0 MWIn study Washington, NYNYISO May 2019target 2026
UN-Kylertown
Solar
20.0 MWAgreement signed Westmoreland, PAPJM Feb 2019target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)