NY13 Solar

NY13 Solar is a 20.0 MW solar request in interconnection study in the NYISO interconnection queue, in Washington County, New York, connecting to NM-NG.

Queue statusIn planning
  1. PlanningQueued May 2019 (current stage)
  2. ConsentedOct 2021 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
855
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Bald Mountain Solar LLC
Connection point (POI)
Mohican - Schaghticoke 115kV
Location
Washington County, New York
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
SIS, FS
Queue status
Active
Entered queue
24 May 2019
Agreement signed
7 October 2021
Proposed online date
June 2027

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.