SOLAR Β· NYISOChamplain Solar
Champlain Solar is a 100 MW solar request withdrawn in the NYISO interconnection queue, in Washington County, New York, connecting to NM-NG.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2021 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1146
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- RWE Clean Energy Development, LLC
- Connection point (POI)
- Mohican - Whitehall 115 kV Line #13
- Location
- Washington County, New York
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Queue status
- Withdrawn
- Entered queue
- 19 February 2021
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Fort Edward Solar Farm (NY53)Solar Β· 100 MW Β· in study
- Somers Solar, LLCSolar Β· 20.0 MW Β· in study
- NY13 SolarSolar Β· 20.0 MW Β· in study
- Dolan SolarSolar Β· 20.0 MW Β· in study
- Branscomb SolarSolar Β· 20.0 MW Β· built
- Darby SolarSolar Β· 20.0 MW Β· built
- Darby SolarSolar Β· 20.0 MW Β· built
- Branscomb SolarSolar Β· 20.0 MW Β· built
- Fort Edward Solar Farm (NY53)Solar Β· 100 MW Β· withdrawn
- Blue Star SolarSolar Β· 100 MW Β· withdrawn
- Fort Edward Solar Farm (NY53)Solar Β· 100 MW Β· withdrawn
- Champlain SolarSolar Β· 90.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem