United States › Grid › Interconnection queues › New York
SOLAR · NYISOFort Edward Solar Farm (NY53)
Fort Edward Solar Farm (NY53) is a 100 MW solar request in interconnection study in the NYISO interconnection queue, in Washington County, New York, connecting to NM-NG.
Queue statusIn planning
- PlanningQueued Aug 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- C24-111
- Grid region
- NYISO (New York)
- Utility / transmission owner
- NM-NG
- Developer
- Fort Edward Solar LLC
- Connection point (POI)
- Mohican to Battenkill 115 kV Line #15
- Location
- Washington County, New York
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Queue status
- Active
- Entered queue
- 29 August 2024
- Proposed online date
- December 2027
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Somers Solar, LLCSolar · 20.0 MW · in study
- NY13 SolarSolar · 20.0 MW · in study
- Dolan SolarSolar · 20.0 MW · in study
- Branscomb SolarSolar · 20.0 MW · built
- Darby SolarSolar · 20.0 MW · built
- Darby SolarSolar · 20.0 MW · built
- Branscomb SolarSolar · 20.0 MW · built
- Fort Edward Solar Farm (NY53)Solar · 100 MW · withdrawn
- Blue Star SolarSolar · 100 MW · withdrawn
- Champlain SolarSolar · 100 MW · withdrawn
- Fort Edward Solar Farm (NY53)Solar · 100 MW · withdrawn
- Champlain SolarSolar · 90.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem