SOLAR · NYISO

Fort Edward Solar Farm (NY53)

Fort Edward Solar Farm (NY53) is a 100 MW solar request withdrawn in the NYISO interconnection queue, in Washington County, New York, connecting to NM-NG.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2023 (completed)
  2. Withdrawn / abandonedFeb 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1516
Grid region
NYISO (New York)
Utility / transmission owner
NM-NG
Developer
Fort Edward Solar
Connection point (POI)
Mohican-Battenkill 115kV Line #15
Location
Washington County, New York
Technology
Solar: 100 MW
Total requested
100 MW
Queue status
Withdrawn
Entered queue
10 February 2023
Withdrawn
February 2023

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in New York · Transmission lines in New York

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem