Limestone Solar

Limestone Solar is a 20.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Union County, Pennsylvania, connecting to PPL.

Queue statusConsented
  1. PlanningQueued Sep 2019 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF1-337
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Laurelton-Mifflinburg 69 kV
Location
Union County, Pennsylvania
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
27 September 2019
Proposed online date
September 2027

Location

Marker shows the centre of Union County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Union County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem