🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 109

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 109 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Texas Clean C
Coal · Summit Energy
240 MWWithdrawn / abandoned ERCOT Mar 2010target 2021
Lewis Run - Pierce Brook 230 kV
Solar · RWE Solar Development, LLC
240 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Solar project 552, Elmore County
Solar
240 MWWithdrawn / abandoned Elmore, IDWest Apr 2019
Other project 734, Baker County
Other
240 MWWithdrawn / abandoned Baker, ORWest Sep 2023target 2028
Rich Road Solar Energy Center
Solar + storage · EDF Renewables Development, Inc.
240 MWWithdrawn / abandoned St. Lawrence, NYNYISO Aug 2024
Onshore wind project GEN-2002-010, Woodward County
Onshore wind
240 MWWithdrawn / abandoned Woodward, OKSPP Jul 2002target 2003
Solar project GI-2018-33, Pueblo County
Solar
240 MWWithdrawn / abandoned Pueblo, COWest Sep 2018target 2021
Solar project 553, Elmore County
Solar
240 MWWithdrawn / abandoned Elmore, IDWest Apr 2019
Solar project 572, Rankin County
Solar
240 MWWithdrawn / abandoned Rankin, MSSoutheast Jun 2023target 2026
Solar project GEN-2021-073, Lancaster County
Solar
240 MWWithdrawn / abandoned Lancaster, NESPP May 2021target 2027
Solar project 765, Iron County
Solar
240 MWWithdrawn / abandoned Iron, UTWest Jun 2016target 2019
Battery storage project AF2-016, Atlantic County
Battery storage · Garden Reserve Energy, LLC
240 MWWithdrawn / abandoned Atlantic, NJPJM Oct 2019target 2023
Solar + storage project J2923, Columbia County
Solar + storage
240 MWWithdrawn / abandoned Columbia, ARMISO Sep 2022target 2028
Onshore wind project GEN-2003-008, Carson County
Onshore wind
240 MWWithdrawn / abandoned Carson, TXSPP Jul 2003target 2004
Solar project GI-2016-7, Pueblo County
Solar
240 MWWithdrawn / abandoned Pueblo, COWest Apr 2016target 2018
Gas project BHCT-G1, Pueblo County
Gas · Black Hills Electric Generation LLC
240 MWWithdrawn / abandoned Pueblo, COWest Feb 2009target 2011
Mccullough Pass Solar Project
Solar
240 MWWithdrawn / abandoned Clark, NVCAISO May 2008target 2013
Onshore wind project GEN-2018-078, Lea County
Onshore wind
240 MWWithdrawn / abandoned Lea, NMSPP Nov 2018target 2021
Solar project IC-544, Laurens County
Solar
240 MWWithdrawn / abandoned Laurens, GASoutheast Nov 2016
Mount Storm Repower BESS 1
Battery storage · Mount Storm BESS 1 LLC
240 MWWithdrawn / abandoned Grant, WVPJM Sep 2021target 2025
Solar project GEN-2017-104, Lea County
Solar
240 MWWithdrawn / abandoned Lea, NMSPP Jun 2017target 2019
Onshore wind project GEN-2003-015, Carson County
Onshore wind
240 MWWithdrawn / abandoned Carson, TXSPP Aug 2003target 2004
Onshore wind project 2007-G6
Onshore wind
240 MWWithdrawn / abandoned West Jun 2007target 2014
Solar project C3-113, Washington County
Solar
240 MWWithdrawn / abandoned Washington, UTWest May 2023target 2027
Onshore wind project GEN-2016-103, Hyde County
Onshore wind
240 MWWithdrawn / abandoned Hyde, SDSPP Nov 2016target 2018
Battery storage project J2585, Greene County
Battery storage
240 MWWithdrawn / abandoned Greene, INMISO Sep 2022target 2025
Battery storage project AG2-451, Salem County
Battery storage · Carneys Point Energy Storage, L.L.C.
240 MWWithdrawn / abandoned Salem, NJPJM Mar 2025target 2024
Onshore wind project GEN-2024-237, Okfuskee County
Onshore wind
240 MWWithdrawn / abandoned Okfuskee, OKSPP Mar 2025target 2029
Dog Creek Wind Farm
Onshore wind
240 MWWithdrawn / abandoned Allen, INPJM Jul 2007target 2016
Onshore wind project GEN-2008-120, Randall County
Onshore wind
239 MWWithdrawn / abandoned Randall, TXSPP Oct 2008target 2011
Sokolata Hybrid
Solar + storage
239 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Onshore wind project G0658, Klamath County
Onshore wind
239 MWWithdrawn / abandoned Klamath, ORWest Oct 2020target 2025
Prairie Switch PV1 SLF
Solar · FRESH AIR ENERGY II, LLC
239 MWWithdrawn / abandoned Wharton, TXERCOT Mar 2023target 2027
battery storage additional (see Q664)
Wind + storage
239 MWWithdrawn / abandoned Franklin, MEISO-NE Jul 2017target 2020
Onshore wind project 1192, Klamath County
Onshore wind
239 MWWithdrawn / abandoned Klamath, ORWest Feb 2020target 2025
Combustion Turbine Generator
Gas
238 MWWithdrawn / abandoned Providence, RIISO-NE Feb 2015target 2020
Palmas C5
Solar
238 MWWithdrawn / abandoned Yuma, AZCAISO Apr 2012target 2014
Palmas (Fka Hyder Solar)
Solar
238 MWWithdrawn / abandoned Yuma, AZCAISO Jul 2010target 2013
Battery Storage
Battery storage
238 MWWithdrawn / abandoned Hartford, CTISO-NE Dec 2023target 2027
Battery Storage
Battery storage
238 MWWithdrawn / abandoned Hartford, CTISO-NE May 2024target 2027
Battery Storage
Battery storage
238 MWWithdrawn / abandoned Bristol, MAISO-NE Aug 2023target 2027
Gas project IC-114, Glynn County
Gas
237 MWWithdrawn / abandoned Glynn, GASoutheast
Buenos Aires 2 W
Onshore wind · Terra-Gen
237 MWWithdrawn / abandoned Hidalgo, TXERCOT Mar 2017target 2021
La Joya II Wind
Onshore wind · Terra-Gen
237 MWWithdrawn / abandoned Hidalgo, TXERCOT Sep 2017target 2022
La Joya I Wind
Onshore wind · Terra-Gen
237 MWWithdrawn / abandoned Hidalgo, TXERCOT Sep 2017target 2022
Onshore wind project J3751, Madison County
Onshore wind
236 MWWithdrawn / abandoned Madison, ILMISO Apr 2024target 2028
Solar + storage project J2650, Hancock County
Solar + storage
236 MWWithdrawn / abandoned Hancock, INMISO Sep 2022target 2027
Powwow
Solar + storage
236 MWWithdrawn / abandoned San Diego, CACAISO Apr 2020target 2022
Robin 3
Solar + storage
235 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Solar project AE1-200, Randolph County
Solar
235 MWWithdrawn / abandoned Randolph, INPJM Sep 2018target 2022
Page 109 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)