Onshore wind project J3751, Madison County

Onshore wind project J3751, Madison County is a 236 MW onshore wind request withdrawn in the MISO interconnection queue, in Madison County, Illinois, connecting to AMEREN ILLINOIS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3751
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMEREN ILLINOIS
Connection point (POI)
7COFFEEN - 7ROXFORD 345.0kV
Location
Madison County, Illinois
Technology
Wind: 236 MW
Total requested
236 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 April 2024
Proposed online date
October 2028
Withdrawn
December 2025

Location

Marker shows the centre of Madison County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Madison County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem