🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 238 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2023 (completed)
  2. Withdrawn / abandonedFeb 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1470
Grid region
ISO-NE (New England)
Connection point (POI)
The Primary Point of Interconnection will be located on the IC’s property (Lat, long: 41°49'19.50"N, 72°43'23.49"W) by tapping the 115-kV Line 1751 (Bloomfield_J-NW.Hartford) at approx. 0.98 km fr
Location
Hartford County, Connecticut
Technology
Battery: 238 MW
Total requested
238 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 December 2023
Proposed online date
January 2027
Withdrawn
February 2024

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Hartford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem