πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 765, Iron County

Solar project 765, Iron County is a 240 MW solar request withdrawn in the West interconnection queue, in Iron County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
765
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Holt substation
Location
Iron County, Utah
Technology
Solar: 240 MW
Total requested
240 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
22 June 2016
Proposed online date
December 2019

Location

Marker shows the centre of Iron County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Iron County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem