πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Oklahoma

ONSHORE WIND Β· SPP

Onshore wind project GEN-2024-237, Okfuskee County

Onshore wind project GEN-2024-237, Okfuskee County is a 240 MW onshore wind request withdrawn in the SPP interconnection queue, in Okfuskee County, Oklahoma, connecting to WFEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2024-237
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
WFEC
Connection point (POI)
Paragon 138 kV Substation
Location
Okfuskee County, Oklahoma
Technology
Wind: 240 MW
Total requested
240 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
1 March 2025
Proposed online date
December 2029
Withdrawn
December 2025

Location

Marker shows the centre of Okfuskee County; the queue data does not give exact sites.

Power plants in Oklahoma Β· Transmission lines in Oklahoma

Other requests in Okfuskee County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem