Home › Grid infrastructure › Connection queue

NESO TEC REGISTER · GREAT BRITAIN

Battery storage projects in the connection queue on the National Grid (England & Wales) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown503151.0 GW in total
In planning360scoping or awaiting consent
Consented or building77closest to connecting
Built66connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

503 projects · page 8 of 11
ProjectCapacityStageConnection siteFrom
Orchard BESS
Battery storage · RE Projects Development Limited
100 MWScoping Staffordshire Connection Node B 132kV Substation
National Grid (England & Wales)
Oct 2037
Taunton
Battery storage · Pivoted Power LLP
100 MWAwaiting Consents Taunton 400kV Substation
National Grid (England & Wales)
Oct 2037
West Common Ipers Lane
Battery storage · West Common BESS Limited
100 MWScoping Solent Connection Node A 132kV Substation
National Grid (England & Wales)
Oct 2038
KXP Alpha One
Battery storage · Kxp Alpha I Limited
100 MWScoping Fawley 132kV Substation
National Grid (England & Wales)
Oct 2036
KXP Alpha Three
Battery storage · Kxp Alpha III Limited
100 MWScoping Fawley 132kV Substation
National Grid (England & Wales)
Oct 2036
KXP Alpha Two
Battery storage · Kxp Alpha II Limited
100 MWScoping Fawley 132kV Substation
National Grid (England & Wales)
Oct 2036
Barge Way 120MW BESS
Battery storage · Fpc Electric Land Limited
100 MWScoping Kemsley GSP
National Grid (England & Wales)
Oct 2033
Barking BESS
Battery storage · O&G Solar (SPV 52) Limited
100 MWConsents Approved Barking West GSP
National Grid (England & Wales)
Oct 2028
Didcot BESS 2
Battery storage · Downing Renewable Developments LLP
100 MWScoping Didcot 132kV GIS Substation
National Grid (England & Wales)
Oct 2037
Elland BESS
Battery storage · O&G Solar (SPV 39) Limited
100 MWScoping Elland 132kV Substation
National Grid (England & Wales)
Oct 2036
J102A Oldbury BESS
Battery storage · RWE Renewables UK Solar and Storage Limited
100 MWScoping Severn Connection Node A 132kV Substation
National Grid (England & Wales)
Oct 2037
KX Alpha 3 Iron Acton
Battery storage · Kxp Alpha III Limited
100 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2037
KXP Alpha 1 Little Horsted
Battery storage · Kxp Alpha I Limited
100 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
KXP Alpha 2 Little Horsted
Battery storage · Kxp Alpha II Limited
100 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
KXP Alpha 3 Little Horsted
Battery storage · Kxp Alpha III Limited
100 MWScoping Sussex and Romney Connection Node A 400kV Substation
National Grid (England & Wales)
Oct 2037
Lakeside Energy Drax
Battery storage · Lakeside Energy Storage Limited
100 MWBuilt Drax 132kV Substation
National Grid (England & Wales)
Norwich 100MW BESS
Battery storage · Flexion Energy Spv 2 Ltd
100 MWScoping Norwich Main 132kV
National Grid (England & Wales)
Oct 2031
Shaftesbury Energy Park
Battery storage · Tagenergy Development UK Limited
100 MWConsents Approved Shaftesbury 132kV Substation
National Grid (England & Wales)
Dec 2036
Thurcroft BESS
Battery storage · Harmony Tc Limited
100 MWScoping Thurcroft 275kV Substation
National Grid (England & Wales)
Oct 2031
Valley Farm
Battery storage · Starlight Energy UK Limited
100 MWScoping Bishops Wood GSP
National Grid (England & Wales)
Oct 2037
Dollymans Storage
Battery storage · Dollymans Storage Limited
100 MWScoping Rayleigh Main 132kV Substation
National Grid (England & Wales)
Jan 2023
Danks Way BESS
Battery storage · Ocker Hill BESS Limited
99 MWUnder Construction/Commissioning Ocker Hill C 132kV GSP
National Grid (England & Wales)
Oct 2026
KX Alpha 1 Iron Acton
Battery storage · Kxp Alpha I Limited
99 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2037
KX Alpha 2 Iron Acton
Battery storage · Kxp Alpha II Limited
99 MWScoping Severn Connection Node A 400kv Substation
National Grid (England & Wales)
Oct 2038
Swansea Greener Grid Park - Connection 1
Battery storage · Swansea Grid Solutions Limited
97 MWScoping Swansea North 400kV Substation
National Grid (England & Wales)
Oct 2028
012 NEP Coventry West
Battery storage · New Energy Partnership Limited
92 MWScoping Berkswell GSP
National Grid (England & Wales)
Oct 2034
Laleham
Battery storage · Juniper Energy Limited
90 MWScoping Laleham 132kV Substation
National Grid (England & Wales)
Oct 2030
Royle Farm BESS
Battery storage · Aludra BESS Ltd
90 MWConsents Approved Drakelow 132kV Substation
National Grid (England & Wales)
Oct 2028
KXP Immingham
Battery storage · Kxp Immingham Limited
80 MWBuilt Grimsby West 400/132 GSP
National Grid (England & Wales)
Weirs Drove
Battery storage · Care Power (Burwell 1) Limited
80 MWScoping Burwell 132kV Substation
National Grid (England & Wales)
Oct 2028
Necton Greener Grid Park
Battery storage · Necton Grid Solutions Limited
78 MWAwaiting Consents Necton 400kV Substation
National Grid (England & Wales)
Oct 2032
Stella Battery Energy Storage
Battery storage · Capella BESS Ltd
78 MWConsents Approved Stella South GSP
National Grid (England & Wales)
Nov 2026
Sellindge (Tertiary)
Battery storage · Pivoted Power LLP
76 MWAwaiting Consents Sellindge 400kV Substation
National Grid (England & Wales)
Oct 2031
Don Cossack
Battery storage · Don Cossack Ltd
70 MWAwaiting Consents Tynemouth 275kV Substation
National Grid (England & Wales)
Jun 2034
Arkwright
Battery storage · Arlington (Group Services) Limited
57 MWScoping Chesterfield 400kV Substation (Not yet constructed)
National Grid (England & Wales)
Oct 2034
Biggleswade BESS
Battery storage · Central Bedfordshire Council
57 MWScoping Biggleswade 400kV Substation
National Grid (England & Wales)
Sep 2029
Capenhurst Tertiary Connection
Battery storage · Hd888Cap Limited
57 MWBuilt Capenhurst 275kV Substation
National Grid (England & Wales)
Bramley BESS
Battery storage · Bramley BESS Limited
57 MWUnder Construction/Commissioning Bramley 400kV Substation
National Grid (England & Wales)
Oct 2037
Burwell (Tertiary)
Battery storage · Pivoted Power LLP
57 MWAwaiting Consents Burwell Main 400kV Substation
National Grid (England & Wales)
Jun 2029
Bustleholme
Battery storage · Pivoted Power LLP
57 MWBuilt Bustleholm GSP
National Grid (England & Wales)
Carrington
Battery storage · Pivoted Power LLP
57 MWAwaiting Consents Carrington 275kV Substation
National Grid (England & Wales)
Oct 2028
Enderby (Akira)
Battery storage · Enderby Battery Storage Limited
57 MWBuilt Enderby 400kV Substation
National Grid (England & Wales)
Fferm Solar Pentir
Battery storage · Lightsource Spv 191 Limited
57 MWConsents Approved Pentir 400kV Substation
National Grid (England & Wales)
Oct 2028
Kirkby
Battery storage · Kirkby Battery Storage Ltd
57 MWConsents Approved Kirkby 275/33kV Substation
National Grid (England & Wales)
Oct 2037
Legacy Tertiary Connection
Battery storage · Hd639Leg Limited
57 MWConsents Approved Legacy 400kV Substation
National Grid (England & Wales)
Aug 2024
Lister Battery (formerly Lister Drive)
Battery storage · Lister Battery Ltd
57 MWConsents Approved Lister Drive 275kV Substation
National Grid (England & Wales)
Sep 2029
Lister Drive Shaw
Battery storage · Carnegie (BES) Ltd
57 MWScoping Lister Drive 275kV Substation
National Grid (England & Wales)
Sep 2026
Native River (Capenhurst)
Battery storage · Native River Ltd
57 MWBuilt Capenhurst 275kV Substation
National Grid (England & Wales)
Mill Hill Tertiary Connection
Battery storage · HB333MIL LTD
57 MWConsents Approved Mill Hill 275kV Substation
National Grid (England & Wales)
Oct 2025
Monets Garden
Battery storage · Monets Garden Battery Ltd
57 MWConsents Approved Osbaldwick 400kV Substation
National Grid (England & Wales)
Jun 2027
Page 8 of 11

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.