Grid infrastructure βΊ Connection queue βΊ Battery storage
BATTERY STORAGE Β· NGETKXP Immingham
KXP Immingham is a 80 MW battery storage project built and connected, connecting to the National Grid (England & Wales) network at Grimsby West 400/132 GSP. The connection agreement is held by Kxp Immingham Limited.
Connection details
- NESO project number
- PRO-005115
- Customer
- Kxp Immingham Limited
- Technology
- Energy Storage System
- Total capacity
- 80 MW
- Already connected
- 80 MW
- Connection site
- Grimsby West 400/132 GSP
- Transmission owner
- National Grid (England & Wales)
- Connection type
- Embedded (connects through the local distribution network)
- NESO project status
- Built
Connection site
The marker shows the connection substation, not the project itself, with the transmission network around it.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem