Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · NGET

Burwell (Tertiary)

Burwell (Tertiary) is a 57 MW battery storage project in planning, connecting to the National Grid (England & Wales) network at Burwell Main 400kV Substation, with capacity due from June 2029. The connection agreement is held by Pivoted Power LLP.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001109
Customer
Pivoted Power LLP
Technology
Energy Storage System
Total capacity
57 MW
Change in this agreement
+57 MW
Capacity effective from
30 June 2029
Connection site
Burwell Main 400kV Substation
Transmission owner
National Grid (England & Wales)
Connection type
Direct connection to the transmission network
NESO project status
Awaiting Consents

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Burwell Main · Grid map

Other projects at Burwell Main 400kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem