NESO TEC REGISTER · GREAT BRITAIN

Grid connection projects in the connection queue on the SSEN Transmission (north Scotland) network

Every generator, battery and interconnector with an agreement to connect to the GB transmission network, from early scoping to built. Filter by technology, stage or network, and open a project for its connection details.

Projects shown444102.5 GW in total
In planning303scoping or awaiting consent
Consented or building52closest to connecting
Built89connected and operating

Map

Loading projects…

Voltage400 kV275 kV132 kVHVDCNew HVAC

ProjectsPlanningConsentedConstructionBuiltMajor project with its own page

Projects

444 projects · page 3 of 9
ProjectCapacityStageConnection siteFrom
Clash Gour
Wind + storage · Clash Gour Windfarm Holdings Limited
210 MWAwaiting Consents Clash Gour Wind Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Strathy South Wind
Onshore wind · Sse Generation Limited
208 MWConsents Approved Strathy South 132/33kV Substation
SSEN Transmission (north Scotland)
Sep 2030
Achies BESS
Battery storage · Igp Energy Storage 5 Limited
200 MWScoping New Spittal 275kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Ardonald Wind Farm
Solar + storage · Ardonald Renewables Limited
200 MWScoping New North East 275kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Blairgowrie BESS
Battery storage · Woodside BESS Ltd
200 MWScoping Blairgowrie BESS 132kV Substation
SSEN Transmission (north Scotland)
May 2030
Broadford BESS
Battery storage · Field Devco Ltd
200 MWScoping Broadford 132kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Cloiche Wind Farm
Onshore wind · Sse Generation Limited
200 MWScoping Cloiche 132/33kV Substation
SSEN Transmission (north Scotland)
Feb 2028
Corriemoillie BESS
Battery storage · Field Corriemoillie Ltd
200 MWScoping Corriemoillie 132kV Substation
SSEN Transmission (north Scotland)
Sep 2029
Dalchork Farm
Battery storage · Qair Renewables UK Limited
200 MWScoping Dalchork 132kV Substation
SSEN Transmission (north Scotland)
Oct 2032
Dounreay BESS
Battery storage · Field Devco Ltd
200 MWScoping New Dounreay 400kV substation
SSEN Transmission (north Scotland)
Oct 2034
Fort Augustus BESS
Battery storage · Field Devco Ltd
200 MWScoping Fort Augustus 400kV
SSEN Transmission (north Scotland)
Oct 2035
Fyrish Battery Storage
Battery storage · Field Fyrish Ltd
200 MWScoping Fyrish 132kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Isenau Four
Battery storage · Isenau Energy Storage Resources Four Limited
200 MWScoping Corriemoillie 132/33kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Knocknagael BESS
Battery storage · Field Knocknagael Ltd
200 MWAwaiting Consents Knocknagael 132kV Substation
SSEN Transmission (north Scotland)
Jul 2029
L48 BESS Burnside
Battery storage · S4 UK DEV LTD
200 MWScoping New Deer 2 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Longside BESS
Battery storage · Baywa R.e. UK Limited
200 MWScoping Peterhead 2 400kV Busbar Extension
SSEN Transmission (north Scotland)
Oct 2033
Lythmore
Solar + storage · Qair Scotland Limited
200 MWScoping Thurso South 275kV Substation
SSEN Transmission (north Scotland)
Oct 2034
Myreton BESS
Battery storage · GPC 1039 Ltd
200 MWScoping Tealing 132kV Substation
SSEN Transmission (north Scotland)
Oct 2028
Netherton Hub Bess
Battery storage · Field Netherton Ltd
200 MWScoping Longside 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
New Deer 2 BESS
Battery storage · Field New Deer Ltd
200 MWScoping New Deer 2 400kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Rigifa BESS
Battery storage · Field Rigifa Limited
200 MWScoping Gills Bay 132kV
SSEN Transmission (north Scotland)
Dec 2029
Salamander Offshore Wind Farm
Offshore wind · Salamander Wind Project Company Limited
200 MWScoping Peterhead 132KV Substation
SSEN Transmission (north Scotland)
Mar 2030
Tolkien Solar Farm
Solar + storage · Tolkien Solar Farm Limited
200 MWScoping Tolkien Farm 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
West Saval Battery Storage
Battery storage · West Saval Battery Storage Ltd
200 MWScoping West Saval Substation 132 kV
SSEN Transmission (north Scotland)
Oct 2030
Womblehill BESS Farm
Battery storage · RE Projects Development Limited
200 MWScoping Womblehill BESS Farm 132kV
SSEN Transmission (north Scotland)
Dec 2029
Zenobe Blackhillock 300 MW
Battery storage · Zenobe Blackhillock Limited
200 MWBuilt Blackhillock 275kV Substation
SSEN Transmission (north Scotland)
Zenobe New Deer Battery Storage
Battery storage · Zenobe Energy Limited
200 MWScoping New Deer 400kV Substation
SSEN Transmission (north Scotland)
Oct 2029
Inveroykel Wind Farm
Onshore wind · Rwe Renewables UK Swindon Limited
191 MWScoping Inveroykel Wind Farm 132kV
SSEN Transmission (north Scotland)
Oct 2031
Muaitheabhal Wind Farm
Hydro and pumped storage · Uisenis Power Limited
189 MWConsents Approved Muaitheabhal 132/33kV Substation
SSEN Transmission (north Scotland)
Dec 2030
Griffin Wind Farm
Onshore wind · Griffin Wind Farm Limited
189 MWBuilt Griffin 132/33kV Substation
SSEN Transmission (north Scotland)
Clune Wind Farm
Wind + storage · Renewable Energy Systems Limited
187 MWScoping Clune 132/33 kV Substation
SSEN Transmission (north Scotland)
Apr 2030
Stornoway Wind Farm
Onshore wind · Stornoway Wind Farm Limited
180 MWConsents Approved Arnish 275kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Dorenell Windfarm
Onshore wind · Dorenell Windfarm Limited
177 MWBuilt Dorenell 132/33kV Substation
SSEN Transmission (north Scotland)
Upper Greenfields BESS
Battery storage · S4 UK DEV LTD
175 MWScoping New Deer 2 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Creag Dhubh Windfarm
Wind + storage · Invenergy Development UK Ltd
171 MWScoping Creag Dhubh Wind Farm and BESS 132kV Substation
SSEN Transmission (north Scotland)
Oct 2033
Limekiln Extension 2
Wind + storage · Boralex Limited
171 MWScoping New Limekiln 132 kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Elchies Wind Farm
Onshore wind · Elchies Wind Limited
170 MWScoping Elchies 132/33kV Substation
SSEN Transmission (north Scotland)
Nov 2028
Gresham House Connagill BESS
Battery storage · Energyhubdevelopments Limited
170 MWScoping New Connagill 275/132kV Substation
SSEN Transmission (north Scotland)
Oct 2031
Scotsburn Road
Battery storage · Tbc 002 Limited
170 MWScoping Fyrish 275kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Highland Wind Farm
Wind + storage · Highland Wind Farm Limited
168 MWScoping Highland Wind Farm 132/33kV substation
SSEN Transmission (north Scotland)
Oct 2030
Limekiln
Wind + storage · Limekiln Extension Limited
167 MWScoping Limekilns 132/33kV substation
SSEN Transmission (north Scotland)
Dec 2030
Glendye Wind Farm
Onshore wind · Glendye Wind Farm Limited
167 MWScoping Glendye Wind Farm Substation
SSEN Transmission (north Scotland)
Apr 2034
Deucheran Hill 2 Wind Farm
Wind + storage · RWE Renewables UK Onshore Wind Limited
165 MWScoping Deucheran Hill 2 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2034
Glen Lednock
Wind + storage · Glen Lednock Wind Farm Limited
165 MWScoping Glen Lednock 132kV Substation
SSEN Transmission (north Scotland)
Nov 2031
Balvedavist 162 Battery Storage
Solar + storage · S4N Spittal Ltd
162 MWAwaiting Consents Spittal 132kV Substation
SSEN Transmission (north Scotland)
Oct 2030
Balinoe Wind Farm
Wind + storage · RWE Renewables UK Onshore Wind Limited
161 MWScoping Balinoe 132kV substation
SSEN Transmission (north Scotland)
Oct 2034
Tioram Wind Farm
Onshore wind · Invenergy Development UK Ltd
160 MWScoping New Carradale 132Kv Substation
SSEN Transmission (north Scotland)
Oct 2037
Ruith Cnoc
Onshore wind · Ruith Cnoc Wind Farm Limited
158 MWScoping New Dalchork 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037
Galileo 12 Limited
Solar + storage · Galileo 12 Limited
151 MWScoping Fetteresso 132kV substation
SSEN Transmission (north Scotland)
Oct 2033
Meall Dearg
Wind + storage · Energyfarm UK Meall Dearg Ltd
150 MWScoping New North West 132kV Substation
SSEN Transmission (north Scotland)
Oct 2037

Sources: NESO Transmission Entry Capacity (TEC) register and interconnector register (downloaded 8 November 2026); NESO Clean Power 2030 network map (existing and planned circuits, substations and network projects); National Grid Electricity Transmission overhead line routes. Contains data from NESO, licensed under the NESO Open Data Licence, and National Grid open data. Projects are placed at their connection substation, not the generating site; projects at new, unnamed “connection nodes” are listed but not mapped.