Grid infrastructure › Connection queue › Solar + storage

SOLAR + STORAGE · SHET

Ardonald Wind Farm

Ardonald Wind Farm is a 200 MW solar + storage project in planning, connecting to the SSEN Transmission (north Scotland) network at New North East 275kV Substation, with capacity due from October 2033. The connection agreement is held by Ardonald Renewables Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2033 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003491
Customer
Ardonald Renewables Limited
Technology
Energy Storage System, PV Array (Photo Voltaic/solar), Wind Onshore
Total capacity
200 MW
Change in this agreement
+200 MW
Capacity effective from
31 October 2033
Connection site
New North East 275kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The connection site could not be placed on the map.

Projects connecting near New North East · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem