Grid infrastructure › Connection queue › Offshore wind

OFFSHORE WIND · SHET

Salamander Offshore Wind Farm

Salamander Offshore Wind Farm is a 200 MW offshore wind project in planning, connecting to the SSEN Transmission (north Scotland) network at Peterhead 132KV Substation, with capacity due from March 2030. The connection agreement is held by Salamander Wind Project Company Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Mar 2030 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-001512
Customer
Salamander Wind Project Company Limited
Technology
Energy Storage System, Wind Offshore
Total capacity
200 MW
Change in this agreement
+200 MW
Capacity effective from
31 March 2030
Connection site
Peterhead 132KV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping

Connection site

The marker shows the connection substation, not the project itself, with the transmission network around it.

Projects connecting near Peterhead · Grid map

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem