Grid infrastructure › Connection queue › Battery storage

BATTERY STORAGE · SHET

Gresham House Connagill BESS

Gresham House Connagill BESS is a 170 MW battery storage project in planning, connecting to the SSEN Transmission (north Scotland) network at New Connagill 275/132kV Substation, with capacity due from October 2031. The connection agreement is held by Energyhubdevelopments Limited.

Project stageIn planning
  1. Planning (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingFrom Oct 2031 (not yet reached)
  5. Closed (not yet reached)

Scoping and awaiting consents are both shown as planning. A connection agreement does not mean the project will be built: many queue projects never reach construction.

Connection details

NESO project number
PRO-003434
Customer
Energyhubdevelopments Limited
Technology
Energy Storage System
Total capacity
170 MW
Change in this agreement
+170 MW
Capacity effective from
31 October 2031
Connection site
New Connagill 275/132kV Substation
Transmission owner
SSEN Transmission (north Scotland)
Connection type
Direct connection to the transmission network
NESO project status
Scoping
Connections reform gate
Gate 1

Connection site

The connection site could not be placed on the map.

Projects connecting near New Connagill · Grid map

Other projects at New Connagill 275/132kV Substation

Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem