Grid infrastructure › Connection queue › Hydro and pumped storage
HYDRO AND PUMPED STORAGE · SHETMuaitheabhal Wind Farm
Muaitheabhal Wind Farm is a 189 MW hydro and pumped storage project consented, connecting to the SSEN Transmission (north Scotland) network at Muaitheabhal 132/33kV Substation, with capacity due from December 2030. The connection agreement is held by Uisenis Power Limited.
Project stageConsented
- Planning (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingFrom Dec 2030 (not yet reached)
- Closed (not yet reached)
Connection details
- NESO project number
- PRO-000272
- Customer
- Uisenis Power Limited
- Technology
- Pump Storage, Wind Onshore
- Total capacity
- 189 MW
- Change in this agreement
- +189 MW
- Capacity effective from
- 31 December 2030
- Connection site
- Muaitheabhal 132/33kV Substation
- Transmission owner
- SSEN Transmission (north Scotland)
- Connection type
- Direct connection to the transmission network
- NESO project status
- Consents Approved
Connection site
The connection site could not be placed on the map.
Source: NESO Transmission Entry Capacity (TEC) register, downloaded 8 November 2026. Contains data from NESO, licensed under the NESO Open Data Licence. Report a problem